Zeila-Asha Addo Road
GOVERNMENT OF SOMALILAND
MINISTRY OF TRANSPORT AND ROADS DEVELOPMENT (MOTRD) & ROADS DEVELOPMENT AGENCY (RDA)
Consultancy services for the feasibility study preliminary and detailed engineering design, Environmental and social Impact Assessment (ESIA) and preparation of Tender documents for upgrading of
Zeila-Asha Addo Road (22km)
Ref No.: S/L/RDA/LFBR/SVS/2019-10/002
ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (Final)
March 2025
CLIENT: |
SOMALILAND ROADS DEVELOPMENT AGENCY (RDA)
|
|
|
FUNDING ORGANIZATION: |
AFRICAN DEVELOPMENT BANK |
|
|
|
|
PROJECT TITLE: |
Feasibility Study, ESIA and Detailed Engineering Design and Tender Document Preparation of Zeila-Asha Addo Road Project
|
|
|
COUNTRY: |
SOMALILAND
|
|
|
REPORT TITLE: |
ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) |
|
|
PROJECT REF. NO: |
S/L/RDA/LFBR/SVS/2019-10/002 |
|
|
Project team |
Team leader |
Nuru Netre |
|
Nega Abrha, Principal Environmentalist |
|
|
Asefa Ashango, Senior Sociologist |
|
Team members |
Desta Tadesse, Hydrologist |
|
Selemon Asefa, Material Engineer |
||
Hilu Kenea, Socio-Economist |
||
Abderhuman, Junior Environmental Engineer |
||
Somaliland Roads Development Agency (RDA) |
Project Implementation Unit |
Abdillahi Ibrahim, Project Manager Jimcale Dahir, Chief Project Engineer Ahmed Mohamed, Project Engineer |
Table of Content
3. LEGAL, REGULATORY AND INSTITUTIONAL CONSIDERATIONS
3.2. Relevant National Policies
3.3. The Relevant International Conventions and Protocols
3.4. Africa Development Bank Operational Safeguard Policy
4.1. Review of Literature, Guidelines, and Previous study
4.3. Stakeholders Consultation
4.4. Method of Impact Prediction and Evaluation
5. BASELINE CONDTION OF THE EXISTING ENVIRONMENT
5.1.5. Water Resources and Drainage
5.1.6. Land use and land cover
5.2.3. Environmentally Sensitive Areas
5.3.2. Demography, Ethnicity, Language and Culture
5.3.3. Population in the Project Area
5.3.4. Economic Activity and Livelihood
5.3.5. Social Services and Infrastructures
6. PUBLIC CONSULTATION AND PARTICIPATION
6.1. Identification of Stakeholders
6.2. Consultation Processes and Outputs
6.3. Summery Consultation Outputs
7. GRIEVANCES REDRESS MECHANISM
7.1. Need for Grievance Redress
7.4. Grievance Management Approach
7.5. Grievance Redress Mechanism
7.7. Role of PAP’s Representatives in Grievance Redress Committee
8. IMPACT IDENTIFICATION AND EVALUATION
8.1. Identification of Impacts
9. IMPACT MITIGATION AND ENHANCEMENT MEASURES
9.1. Positive Impacts of the Project
9.1.1. Local Income-generation During Construction
9.1.5. Local Social and Socio-economic Benefits during Operation
9.2.1. Impacts on Water Pollution from Sanitary and other Wastes and Spillages
9.2.2. Impacts of Competition for Water Resources
9.2.3. Impacts on Natural Vegetation
9.2.4. Impact on Land Resources
9.2.7. Impacts of Public Health and Safety
9.2.8. Impacts of occupational Health and Safety
9.2.9. Impacts on Wildlife Corridor
9.2.10. Impacts of Coastal land plain Activities on Red Sea
9.2.11. Impacts of Construction Spoils
10. OUTLINE ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP)
11. Conclusion & Recommendations
11.1. Key Aspects to Include in Bidding Documents
ANNEX I List of Contacted Officials/Persons
ANNEX III Minor drainage structures on the Zeila-Asha Addo road project
ANNEX III Minutes of Meeting during public consultation
List of Tables
Table 1 Summary of Major Impacts and Mitigation Measure
Table 2 Comparison between Do nothing & Construction of the road
Table 3 Comparison of construction technologies (option & option)
Table 4 the Project Description
Table 5 Geographic location of Towns along the Project Road
Table 6 Relevant National Acts & Policies
Table 7 Relevant International Conventions & Protocols
Table 8 Applicable AfDB Operational Safeguards (OS1-Os10)
Table 9 Institutional Framework relevant to the implementation of the project
Table 10 Pictures showing flat of the project
Table 11 Vegetation type in the Zeila-Asha Addo Road Project
Table 12 Major wildlife species in the project area (fauna)
Table 13 Settlements along the proposed corridor
Table 14 Water sources along the proposed corridor
Table 15 Health Facilities alongside the road project
Table 16 Health professionals alongside the road project
Table 17 Number of Schools alongside the road project
Table 19 Environmental and Social Management Plan
List of Figures
Figure 1 Location Map for Zeila-Asha Addo Road Project (Line 2B)
Figure 2: Nature of an Environmental Impact before and After Project Initiation (Glasson, 1999)
Figure 3: Showing Topography (Elevation) along the project area
Figure 4 Geological map of the project area (Source Geological Map of Somali land)
Figure 5 Pictures depicting soils in the project area/ On the Coastal low lands
Figure 6 Water Source along the Route on the low coastal plain
Figure 7 Watershed map of Road Project
Figure 9 Pictures illustrating the Flora of the project area (Coastal land vegetation)
Figure 10 Pictures illustrating consultation
Acronyms and Abbreviations
ADB |
African Development Bank |
SE |
SABA Engineering |
CBO |
Community Based Organization |
CBD |
Convention on Biological Diversity |
CPA |
Comprehensive Peace Agreement |
EHS |
Environmental Health Safety |
EIA |
Environmental Impact Assessment |
ESIA |
Environmental and Social Impact Assessment |
ESAP |
Environmental and Social Action Plan |
ESMP |
Environmental and Social Management Plan |
FGD |
Focus group discussions |
GoSL |
Government of Somali Land |
MoAL |
Ministry of Agriculture and Livestock Development |
MoH |
Ministry of Health |
MoLPSHRM |
Ministry of Labor, Public Service and Human Resources Management |
NGO |
Non-Governmental Organization |
PPP |
Polluter pays Principle |
SLRA |
SomalilandRoads Authority |
RAP |
Resettlement Action Plan |
SLDP |
SomalilandDevelopment Plan |
TA |
Traditional Authority |
UNFCCC |
United Nations Framework Convention on Climate Change |
WB |
World Bank |
EXECUTIVE SUMMARY
Introduction and Background
The demand for roads within Somaliland has increased tremendously as the mobility of urban, suburban and regional commuters has increased, as has the transport of assorted agricultural produce, industrial raw materials and finished products. The demand has further increased since road transport has become the means of personalized transport. The remarkable economic growth achieved in the last few years by most developing countries in the Horn of Africa and the East African region has put a daunting pressure on infrastructure development, of which roads are the starting point. Consequently, the construction, expansion and upgrading of the national road (Zeila-Asha Addo in Somaliland) network was already a major aspect of the economic development program in Somaliland in and in the Horn of Africa countries.
The Somaliland Roads Authority acting as a duly representative of the Ministry of Transport and Road Development of the Government Republic of Somaliland in the road sector decided to construct the Zeila-Asha Addo Road Project. Pertinent to the above concept the Government of the Republic of Somaliland, represented by the Somaliland Roads Authority, an implementing agency of the Transport and Road Development, has been allocated grant funds from the African Development Fund towards Feasibility studies, Environmental and Social Impact Assessment, Resettlement Action Plan (RAP), Detailed Engineering Design, Cost Estimates and Preparation of Bidding Documents for Upgrading to Paved (Bitumen) Standard of Zeila-Asha Addo Road Project(22km).
The above mentioned project will be part of Borama-Hargeissa corridor. The project road Zeila-Asha Addo road starts at Ziela town, which is located in Eastern part of the Awdal region. The start point of the project is around 270km North East of Borama. The geographic coordinates is start and end point of the project road are Easting 333469 Northing 1255372 and Easting 329751 and Northing 1235409 respectively. The road will solve the prevailing nationwide transportation cost, transportation efficiency and serve as strategic link between Somaliland, Ethiopia and Djibouti, the link is approximately 15km away from Zeiela.
The Road Development Agency believes that infrastructure development and environmental protection should go hand in hand. ESIA is understood as an integrated part of the planning and construction process devoted to characterize socio-environmental impacts due to the realization of a project. It also seeks to define policies and strategies required to monitor and control such impacts. Hence, in order to understand the impact of the proposed road project on various socio-environmental factors and to propose appropriate measures to overcome adverse impacts, ESIA is taken as part of the Zeila-Asha Addo road project. According to the AfDB’s Integrated Safeguards System (ISS), which has operation safeguards / systems 1-10 (OS 1 – OS 10), the project is classified as Category 1 which calls for a full ESIA to be carried out.
Institutional and Legal Frameworks
Somaliland has been functioning as an independent state since 1991 despite the lack of international recognition. In pursuance of the resolutions of the Conference of the Somaliland Communities held in Burao on 27th April to 5th May 1991, which reaffirmed (their) independence with effect from 18th May 1991; and noting that the Conference of the Elders of the Somaliland Communities held in Borama from 24th January to 25th May 1993 adopted a National Charter. Therefore, cognizing the major reasons of paramount importance Country level through judicial procedures including National beliefs and cultural aspirations and through participation of all stakeholders; the people of Somaliland approved on 31st May, 2001
There are also different relevant policies and strategies:
- National Environment Policy, 2015
- Macro-economic Policy Issues
- National water policy
- Somaliland Tenure policy
- National Forestry and Wildlife Conservation Low-Act No. 69/2015
- International Conventions and
- Polluter Pay Principle (PPP), 1974
- Convention of Biological Diversity
- The United Nations Framework Convention on Climate Change (UNFCCC)
- The World Commission on Environment and development
- The Rio Declaration
- Africa Development Bank Policy; Bank’s Operational Safeguard.
Major Institutional that are applicable to the project are:
At the national and state level, The Ministry of Transport, The Ministry of Environment and Rural Development and the RDA are the most responsible organ in coordinating and organizing the implementation of the project. Zeila district administration together with the sectorial representatives such as education, health, agriculture including the security will play a vital role in assisting the implementation of the project through creating conducive atmosphere in regard to security and close follow up during project implementation. The Ministry of Environment importance shall be involved protecting the environment and sustainable development.
The African Development Bank (AfDB or the Bank) through its Bank’s Operational Safeguard shall assist the project in funding and overall monitoring and evaluation of the project road. The implementation of the project shall be influenced by various international organizations through their International guidelines, agreements, conventions and treaties that have environmental implications/provisions and as such cannot be contravened during project development phases.
ESIA objectives
The fundamental objective of this ESIA is to ensure that upgrading of the project is environmentally sound and contributes to the development. This report provides information on major environmental issues which needs due consideration during construction and operation stages of the project. It is also expected to provide a means whereby the overall environmental performance can be enhanced through.
- Identification and evaluation of the potential impacts associated with the project implementation and operation
- Preparation of plans and recommendations regarding measures that would minimize the adverse impacts and enhance the beneficial impacts.
Summary of the existing Environment to be impacted by the road project
Physiographic Setting: Zeila-Asha Addo road upgrading project is located on the Northern part of the Somaliland. The elevation of starting point is about 0 m above sea level, while that of end of the project is about 4 m above sea level. The proposed project centreline passes through flat terrain.
Population: There is no exact statistics defining the demography of the Country. The population of Awdal region, where the project road corridor is located is estimated at 673,264 (UNFPA 2014).
Climate: The project area is located in the then Awdal region and the current Salal Region in the Coastal plain zones where hot climate is predominating. The Coastal Plain is the zone with high temperatures and low rainfall. Summer temperatures in the region over 38 °C. However, temperatures come down during the winter as it reaches up to 45 °C during the hottest days. The climatic condition of the project area lies is arid. The average annual rainfall in the region is 446 millimetres (17.6 in) while the coastal zone, which is arid climate and receives less precipitation than the surrounding area. The major, rainy season (late March, April, May, and early June) experiences the heaviest rainfall in the coastal range gets rain while the plateau and the mountainous area are in dry condition.
Geology: Near the coast these terrestrial deposits merge into littoral marine deposits. Stratigraphically the plain is divided into four concentric zones, truncated by the sea coast: (i) the Older Boulder Beds; (ii) the younger gravels; (iii) the Zeila plain "laterite"; and (iv) the Coastal Marine beds.
Soil Type: In the low lying flat lands and coastal plains Alluvial and colluvial deposits are soils which are deposited after transportation by means of water and gravity respectively. Mostly alluvial and colluvial deposits in the project stretch are found in the valley and flat topography. Sand, silt and clay intermixed with gravel sized rock fragments are the dominant lithologies.
Land use and Land Cover: The land use on the Zeila and Asha Addo town areas is with occurrence of few housing units utilities include telephone and electric poles. However, The ROW problem is insignificant in the rural areas in between Zeila and Asha Addo or ROW obstruction is expected in Ashado town only in the whole stretch from Zeila to Ash Addo as settlements are very sparse.
Fauna and Flora: The vegetation has adapted to these severe ecological conditions and consists mainly of Xerophyllous species with a mosaic of grassland, bush land and scrubland. The impact on land use is dependent on the encroachment to new land where those vegetation resources are available. In the low land coastal plains, the vegetation occurrence is very sparse in the saline plain but the hard grass, which is adaptable to saline environment occurrence is cosmopolitan.
Environmental Impacts and Mitigation Measures
Both beneficiary and adverse socio-environmental impacts are anticipated from the road development project. The implementation of the project will create employment besides the contribution to the improvement of economic development of the Republic of Somaliland such import and export opportunities and facilities as it will be linked to the Ethiopia-Somali Land-Djibouti corridor.
Table 1 Summary of Major Impacts and Mitigation Measure
CONSTRUCTION |
|||||
Predicted Impacts |
Proposed Measure |
Responsible body |
Estimated Cost, USD |
M& E Indicators |
Time line |
Negative Impacts |
|||||
Properties of 40 project affected people-PAPs could be expropriated. This impact high in towns |
|
Designer, RDA, Contractor, Supervisor |
Included in Design and RAP costs;
|
Complaints from PAPs |
Construction |
Vegetation removal along the Road (within right-of-way), access roads, quarries, borrow areas, etc. |
|
RDA, Contractor, Supervisor |
51000 |
Number of trees planted/ removed |
Construction |
Impediment to movement of wildlife and accidents involving wildlife moving Ostrich, Salt’s dick dick in the project road corridor. |
|
Designer, RDA, Contractor, Supervisor |
18,000 |
Number of accidents |
Construction |
Pollution of surface and ground water as a result of earthwork operations and improper handling of hazardous materials |
|
Designer, RDA, Contractor, Supervisor |
Inincluded in Design and construction cost |
Occurrence of fuel and lubricants contamination |
Construction |
Conflict on water source computation with locals |
|
Contractor |
included in construction cost |
Construction water availability and local people complaints |
Construction
|
Impact on public health safety |
|
Designer, RDA, Contractor, Supervisor |
22,000 |
Cleanliness of Camps and workplaces
Management of Waste disposal
KAP survey and awareness status |
Contactor |
Improper waste (solid as well as liquid) management will cause health problems |
|
RDA, Contractor, Supervisor |
15,000 |
Periodic inspection of solid and liquid disposal in camp site |
|
Impact on occupational health and safety |
|
RDA, Contractor, Supervisor |
Included in construction cost |
Periodic inspection at camp site and areas where heavy machinery works are accomplished |
|
Impact of Construction spoils |
|
RDA, Contractor, Supervisor |
included in construction cost |
Periodic Inspection of Site Management of waste |
Construction |
Impact of Air pollution |
|
RDA, Contractor, Supervisor |
included in construction cost |
Inspection on Frequency of watering, gas emission and management of waste |
Construction |
Impact of Noise |
|
RDA, Contractor, Supervisor |
included in construction |
Inspection equipment’s and provision of PPE to workers |
Construction |
Impacts of Coastal land plain Activities on Red Sea |
|
RDA, Contractor, Supervisor |
included in construction |
Waste management, sediment load and area covered by grass |
Construction |
Total Cost |
106,000 |
|
|
Public Consultation
Major stakeholders identified with whom consultation was made include: Ministry of Transport and Road development, Road and Tranport Agency (RDA), Borama Region and major institutions (health, education, water), political class (deputy governor), local administration (area chiefs) and Zeila District Administration, as well as members from the community of Asha Addo and its surrounding villages. Methods implemented to conduct consultation was Focus group discussion (FDG) in Borama and Zeila stakeholders’ meetings and questionnaires and interviewing sectoral professionals was implemented to gather sectorial information in Borama, the regional capital from March 17/20121 till March 19/2021. Additional consultations were done by project team on 7th April 2025. The discussions during the public consultations focused on the following issues: the progress on the implementation of the road project; the construction timelines; the impact on the community and the environment; preparedness of the community as well as resettlement and compensation. Major outputs of consultation both Zeila and Borama attendants underlined the route should go via Zeyila town as it is the historical port and regional capital of Selal. Major outputs from Borama Region sectoral instructions are also gathered and use to develop baseline information of this ESIA.
Environmental Mitigation and management cost
In this report, the impacts are assessed and quantified. As far as the proposed mitigation measures are implemented properly, the overall project impact would be acceptable and positive impacts would overcome the adverse negative impacts. The overall environmental ESMP cost RAP cost is estimated to be approximately USD 106,000.00, USD 1,020,617.18 respectively.
Conclusion and Recommendation
According to the AfDB’s Integrated Safeguards System (ISS), which has operation safeguards / systems 1-10 (OS 1 – OS 10), the project is classified as Category 1 which calls for a full ESIA to be carried out. The road project is technically and economically feasible. If the benefit enhancement and mitigation measures recommended in this Environmental Impact Statement are adopted, there is no environmental ground for not proceeding with implementation of the project in the form in which it is presently envisaged. Such a worth full road upgrading development, which will bring net benefit of improving import and export to Nation in general and the improvement of living standard of local communities in particular, should be implemented at the earliest possible date.
1.1. Introduction and Purpose
The Zeila-Asha Ado Road project has been selected to pass through detailed Feasibility Study, Environmental and Social Impact Assessment, RAP, Detailed Engineering Design, Cost Estimates and Preparation of Bidding Documents for upgrading to Paved (Bitumen) Standard, which is needed to establish the fully substantiated detail economic justification for alternate types, rehabilitation measures and investment strategies for the specified project.
The construction of Zeila-Asha Addo road project shall provide The Zeila-Asha Ado Road project connects Zeila and Asha Addo. In order to create smooth transportation system, RDA has planned the captioned road for the passenger’s traveling from Zeila to Asha Addo and vice versa. The road serves also as a strategic link with the proposed Lowyiaddo-Borama, which is linked to the Somaliland Capital Hargessa.
The Somaliland Roads Development Authority (RDA) believes that infrastructure development and socio-environmental protection should go hand in hand. ESIA is understood as an integrated part of the planning process devoted to characterize socio-environmental impacts due to the upgrading of a project. It also seeks to define policies and strategies required to monitor and control such impacts. Hence, in order to understand the impact of the proposed road project on various physical, biological and socio-environmental factors and to propose appropriate measures to overcome adverse impacts, ESIA is taken as part of the project feasibility study.
The fundamental objective of this ESIA report is to ensure that upgrading of the project is environmentally sound and contributes to the development. It is also expected to provide a means whereby the overall environmental performance can be enhanced through.
- Identification and evaluation of the potential impacts associated with the project implementation and operation
- Preparation of plans and recommendations regarding measures that would minimize the adverse impacts and enhance the beneficial impacts.
1.2. Analysis of Alternatives
Alternative comparison was done 1) between do nothing scenario versus construction 2) construction technologies including Option1: Complete reconstruction & widening with double surface (DST) versus Option2: Complete reconstruction with asphalt concrete dressing with their advantages & disadvantages. The comparison between do nothing versus constructing the road and the comparison of construction technologies (option 1 and 2) is given on Table 2 & Table 3 respectively together with summarized conclusion as below.
Table 2 Comparison between Do nothing & Construction of the road
Alternatives |
Advantage |
Disadvantage |
Do nothing |
The overall impacts on E&S will not occur: Vegetation clearing, habitat destruction, Air pollution, water pollution, waste generation, depletion of natural resources, vulnubrity of local’s property destruction/loose.
|
All the advantages happening during construction will not occur and local communities will loss all the socioeconomic advantages getting from the construction of the road in particular & the whole region/Country in general |
Construction |
Increase travel time, reduction transport cost & maintenance cost, ease procedures & wide coverage, provide real solution for human need, serve connected area for prolonged period of time, provide community with job creation and business opportunity and provide social and economic friendliness |
Impacts such as vegetation clearance &habitat destruction, water air & noise pollution, depletion of natural resource, destruction of local community properties, disruption of local community, safety risks (workplace hazard & public safety).
Others are, regulatory challenges (permit delay & compliance cost), project management & challenges & long term maintenance costs. |
Table 3 Comparison of construction technologies (option & option)
Construction technologies options |
||
Advantage |
Advantage |
Advantage |
Option: Complete reconstruction & widening with double surface (DST) |
When double bituminous surface treatments are properly designed and constructed, a relatively inexpensive pavement surface can be produced which will provide satisfactory performance for several years with minimum maintenance costs. Cost-Effective:- Asphalt is typically less expensive to install than concrete.
Faster Installation: - It can be laid and opened to traffic more quickly than concrete, which is beneficial for roadwork and construction projects.
Easier Repairs: - Damaged sections can be more easily repaired or resurfaced. Better Traction:- Asphalt surfaces generally provide better traction, which can be important for safety. |
Hot asphalt cement, used on most jobs, attain the temperature of the substrate to which it is applied in a few seconds. If the substrate is cold, the asphalt cement hardens almost immediately and will not grip the aggregate. Horter Lifespan: - Asphalt typically lasts 15-20 years, requiring more frequent replacement compared to concrete. Higher Maintenance Needs: - It requires more regular maintenance, including sealing and resurfacing.
Heat Sensitivity: - Asphalt can soften in high temperatures, leading to rutting and deformation. Environmental Concerns: - The production of asphalt involves petroleum, which raises environmental concerns, and it can absorb heat, contributing to urban heat islands. Bitumen impact includes high-temperature hazards, emissions of volatile organic compounds and polycyclic aromatic hydrocarbons, and challenges in transportation, such as greenhouse gas emissions and potential spills. |
Option2: Complete reconstruction with asphalt concrete dressing |
Durability:-Concrete pavements tend to have a longer lifespan than asphalt, often lasting 30 years or more with proper maintenance. Low maintenance:-They require less frequent maintenance compared to asphalt, which can degrade more quickly. Load-Bearing Capacity:- Concrete can support heavier loads, making it ideal for high-traffic areas and industrial applications Heat Resistance:-Concrete is more resistant to softening in high temperatures, making it a better choice in hot climates. Reflectivity:-Lighter color reflects more sunlight, which can help reduce heat island effects in urban areas. |
Initial Cost: - The initial installation cost of concrete is generally higher than asphalt. Longer Curing Time: Concrete takes longer to cure, which can delay opening a newly paved road to traffic. Brittleness: - Concrete can crack under certain conditions, such as freeze-thaw cycles or heavy impact. Limited Flexibility:-Once set; it cannot be easily repaired or modified.
|
Conclusion:- Both asphalt and concrete have environmental impacts, including greenhouse gas emissions and energy consumption. However, asphalt has a greater impact due to its petroleum-based composition.
DST uses asphalt binder material and mineral aggregate & concrete causes damages to the most fertile layer of the earth, the top soil. Concrete is more recyclable than asphalt, which makes it a more sustainable choice. However concrete is more resistant to high temperatures than asphalt. Asphalt can soften and deform under extreme heat, leading to ruts and surface damage. Concrete has a longer lifespan and is less prone to cracking and deterioration compared to asphalt, especially under the stress of high temperatures and UV exposure. Therefore, from environmental perspectives and climate of the project area Option2: Complete reconstruction with asphalt concrete dressing is proposed to be more feasible construction technology.
Availability of road construction materials
Initial investigations indicate that there are several possible sites, on the Asha Addo-Areweren stretch, next section from Zeila to Asha Addo that can yield adequate construction materials. A through material investigation should be conducted to confirm or refute this assentation. There was however no discernible indicator of surface water during the dry season in the absence of which thorough hydrological survey is necessary to assess the ground water potential of the road alignment.
The Project Road Zeila-Asha Ado is found in Salal regions of the Republic of Somaliland. The distance between Zeila to Asha Addo is 22 Km by road. The project road is in some cases very narrow (4-6 metres) and requires encroachment both sides to attain the intended standard. The Zeila-Asha Ado Road is an important trade road which connects Djibouti, North Somaliland, and Ethiopia with a significant regional integration and economic development potential. From start to end, the project road crosses Zeila and Asha Addo. The geographic coordinates is start and end point of the project road are Easting 333469 Northing 1255372 and Easting 329751 and Northing 1235409 respectively, the elevation of starting point is about 0 m above sea level, while that of end of the project is about 4m above sea level. The proposed project centreline passes through flat terrain. After its completion, the upgraded road will improve the overall socio-economic aspect of the Republic of Somaliland and contribute its own share towards reducing travel time, maintenance cost and the riding quality of traffic movement along the route. The following Table shows the project description.
Table 4 the Project Description
Description |
|
Carriageway |
7 meter |
Width |
10 meter |
Shoulder width |
1.5 meter |
Pavement type |
Asphalt Concrete (AC) |
Construction Technology |
Machine based and labour |
Parking Lane (m) |
3.5 m |
Walk way width (m) |
2.5m |
Ditch |
On each side |
Along the route, there are two towns. Detail of towns along the road is shown on the table bellow
Table 5 Geographic location of Towns along the Project Road
Village/Town Name |
Geographical location UTM Zone 38N Datum WGS84 |
|||
Easting |
Northing |
Elevation |
||
1 |
Zeila |
333469 |
1255372 |
2 |
2 |
Asha Addo |
329751 |
1235409 |
4 |
|
Figure 1 Location Map for Zeila-Asha Addo Road Project (Line 2B)
3.1. General
This chapter provides an overview of the legal, regulatory, and institutional framework pertinent to environmental management policy, Environmental Impact Assessment (EIA) legislation and procedures in the Somaliland, and the Integrated Safeguards System (OSs) of the African Development Bank triggered by the project. Additionally, it outlines relevant international conventions, treaties, and protocols ratified by the country, as well as the African Development Bank's (AfDB) Operational Safeguards policies and standards that will guide the development and implementation of the Environmental and Social Impact Assessment (ESIA).
3.2. Relevant National Policies
The relevant national policies that will guide the project implementation are given in Table 4.1.
Table 6 Relevant National Acts & Policies
Legislation |
Interpretation of Legislation |
Relevance to the Project |
Enforcing institution |
The Constitution of Somaliland |
Article 12: about natural resource Article 18: Environment and disaster Relief Article 31: Rights of private property Article 34: Citizen’s duty to care and protect environment |
The constitution provides more details about the development and implementation of ESIA |
The Govt. of Somaliland/ Ministry of Transport and Road Development |
National Environment Policy, 2015 |
Provide a framework management guide for the management of Somaliland’s environment and natural resources |
The Project must ensure that all components regarding environment and natural resource are addressed and protected during project implementation |
The Ministry of Environment and Rural Development |
National Water Policy |
Provide general guidance for any actor when preparing its intervention include environmental sustainability, local management s: equitable water use |
The project must consider water resource utilization, pollution and water resource computation |
Ministry of Mining, Energy and Water Resources |
Somaliland Tenure Policy |
Declares land is national property and the state responsibility. The protection and the best means of the exploitation of these natural resources shall be determined by law. |
All lands in Somaliland are administered under this policy, which includes the Project site. |
Ministry of Agriculture and National Urban Land Planning Committee |
National Forestry and Wildlife Conservation Low-Act No. 69/2015 |
This Act provides guiding principles for management and conservation of forest resources, wildlife and wildlife reserve areas |
The Project must ensure that biodiversity is well protected and managed during all phases. |
Ministry of Environment and Rural Development |
The Coastal and Marine Resource Policy of Somali Land |
Provide guiding principles to protect the rich biodiversity of Somaliland’s marine and coastal environments through developing partnerships with stakeholders, communities and local authorities |
It provides principle to meet both international and regional obligations to marine and coastal matters & project must consider during the development & implementation of ESIA |
Ministry of Livestock and Fishery Development |
3.3. The Relevant International Conventions and Protocols
Table 7 Relevant International Conventions & Protocols
Treaty, Agreement, Convention |
Relevance to the project |
Polluter Pay Principle (PPP), 1974 |
Project will be implemented by complying the principle through protecting the environment from pollution as the polluters must pay. |
Convention of Biological Diversity (CBD) |
The project may impact biodiversity through land clearing and land use changes. Project planning would ensure that the project takes appropriate measures to minimize potential impacts on biodiversity. |
The United Nations Framework Convention on Climate Change (UNFCCC)
|
The project will incorporate climate change resilient adaptation while implementing the ESIA. Project will be implemented by complying climate protection principles to prevent greenhouse gas concentrations in the atmosphere/air pollution. |
Underscore that environmental issues are best handled with participation of all concerned citizens at all the relevant levels. |
Project owners shall encourage & facilitate public participation by making information related to environmental concerns to public making information widely available.
|
3.4. Africa Development Bank Operational Safeguard Policy
The Zeila-Asha Addo road project expects that the Africa Development Bank (AfDB) will finance the Project. AfDB likely require the Project to comply with applicable international environmental and social sustainability guidelines & standards. The AfDB has articulated a comprehensive approach to integrate environmental and social considerations into the implementation of development projects. Ensuring environmental and social sustainability is pivotal for achieving successful development outcomes, and the AfDB is committed to systematically mainstreaming these considerations, especially the updated AfDB’s Integrated Safeguards System (ISS) into its Program and Project Management Cycles.
Table 8 Applicable AfDB Operational Safeguards (OS1-Os10)
AfBD Operational Safeguards |
Description |
Relevance to the Project |
OS 1: Assessment and Management of Environmental and Social Risks and Impacts |
Sets out the Bank’s overarching requirements to identify, assess, and manage &monitor potential environmental and social risks and impacts of a project. It guides borrowers to conduct ESA of the project including legal & institutional analysis; concise existing E&S project description, stakeholder’s engagement & information disclosure; develop ESMP & implemental measures, and conduct monitoring and reporting E&S performance. Requirements include climate change vulnerability assessment; public consultation; appraisal and treatment of vulnerable groups; and grievance procedures. OS1 requires that the siting, design, construction, and operation of projects should avoid significant damage of E&S. |
The project aligns with OS1 by necessitating thorough environmental and social impact assessments, incorporating concise existing project description, legal7 institutional analysis, E&S risk analysis, consultation & participation, grievance redress mechanism & accountability, developing ESMP and proposing E&S measures,
|
• OS 2:abour and Working Conditions |
The policy outlines the need for contractors and other actors to: protect workers’ rights; establish, maintain, and improve the employee–employer relationship; protect the workforce from inequality, social exclusion, child labor, and forced labor; establish requirements to provide safe and healthy working conditions.
It outlines the protection of workers (women, persons with disabilities, children of working age. Prevent the use of forced labor & child labor, migration workers, community workers, primary supply workers |
The project aligns with OS2 by prioritizing the protection of workers' rights, ensuring a healthy and safe working environment, and preventing forced labor such as child labor and forced labor. It emphasizes maintaining positive employee-employer relationships and protecting the workforce from social inequalities. |
OS 3: Resources Efficiency Prevention and Management and Pollution |
It recognizes that economic activities often cause air, water, and land pollution, and consume finite resources that may threaten people, ecosystem services, and the environment at the local, regional, and global levels. It includes the efficient and effective resource use, pollution prevention, and GHG emission avoidance.
It guides also the borrower to assess and evaluates the potential impacts of pollutant discharges and resulting ambient concentrations to the environment on the potential receptors |
The project aligns with OS3 by assessing the resources (land, water, material sources (quarry & borrow areas) whereby the intervention induces impact on people, ecosystem and the project environment as a whole.
Project shall assess & analyze land resources, project activities and the impact on receptors including air, water, land resource pollution & their control measures. |
OS 4: Community Health, Safety, and Security |
OS4 recognizes projects, activities, equipment & infrastructure increase community exposure to risk of impacts. It entails the exacerbation of impacts for a community already subjected to impacts from climate change. It also addresses health, safety, security risks of PAPs & their corresponding responsibility of borrowers. Ensure that the safeguarding of personnel and property through the provision of public or private security. |
Project must ensure the consideration of impacts due to project activities, equipment employed and the existing infrastructure including the risk of impacts posed as the result of interaction such as air pollution & noise pollution & proposing the mitigation measures.
Project client should also ensure that the safeguarding of personnel an property through assigning public security |
OS 5:Land Acquisition, Restrictions on Access to land use, and Involuntary Resettlement |
It recognizes project-related land acquisition, restrictions on land access or land use, and loss of property/assets can have adverse impacts on communities and persons such as physical displacement (relocation, loss of residential land or loss of shelter) Therefore it Seeks to ensure displaced persons due to Project activities are treated fairly, equitably, and in a socially and culturally sensitive manner; that they receive compensation and resettlement assistance so that their standards of living, income-earning capacity, production levels, and overall means of livelihood are improved; and that they share in the benefits of the project. |
This OS is triggered by the operations and activities of the captioned road project as there will be 40 involuntary resettlements, displacement, and compensation that commensurate their lost properties
|
OS 6: Habitat and Biodiversity Conservation, and Sustainable Management of living Natural Resources |
The policy prescribes requirements to identify and implement opportunities to conserve and sustainably use biodiversity and natural habitats. |
The project aligns with OS6 by incorporating measures to identify and implement opportunities for biodiversity conservation and sustainable use of ecosystems, recognizing the importance of preserving natural habitats. |
OS 7: Vulnerable Groups |
OS 7 views economic and social rights as an integral part of human rights, and respects the principles and values of human rights It also encourages Borrowers to observe international human rights norms, standards, and best practices in this regard. It gives focus on individuals who are at high risk to recover from project risks. Vulnerability is seen in the context of (i) exposure to risk and adverse impacts; (ii) sensitivity to these risks and impacts; and (iii) adaptive capacity. |
Project should ensure giving special attention to vulnerable groups such as female headed household, disable and elder household heads and provide special assistance either through giving job opportunity or income generation mechanisms. |
OS 8: Cultural Heritage |
It recognizes that cultural heritage is an inherent and essential part of self-identification, and that it provides continuity in tangible and intangible forms between the past, present, and future. People identify with cultural heritage as a reflection and expression of their constantly evolving values, beliefs, knowledge, and traditions.
protect cultural heritage from the adverse impacts, cultural heritage as an integral aspect of sustainable development & meaningful consultation is required |
Project aligns to identify the availability culture heritage by employing meaningful consultation & protecting the same from adverse impacts |
OS9 Financial Intermediaries |
|
This project does not trigger financial intermediary. |
OS 10: Stakeholder Engagement and Information Disclosure. |
Recognizes the importance of open and transparent engagement between the Borrower and project stakeholders as an essential element of good international practice.
Effective stakeholder engagement can improve the environmental and social (E&S) sustainability of projects, enhance project acceptance, and make a significant contribution to successful project design and implementation. This OS is complementary of OS1 Stakeholder engagement is an inclusive process conducted throughout the project life cycle & complements with OS2, OS4, OS5,OS7 and OS8 |
Project must ensure effective stakeholders engagement to improve E & S sustainability, enhance project acceptance at all level and all phases. |
3.5. Institutional Framework
The institutional framework including the RDA, which is the most responsible organ in coordinating and organizing the implementation of the project at the national label, is given under Table 4.4 below.
Table 9 Institutional Framework relevant to the implementation of the project
Institutions/ Implementing Entity |
Specific Roles and Responsibilities |
Interests and roles in this Project Implementation |
Level of intervention |
Ministry of transportation & Road Development |
The Ministry also provides policy and strategic guidance to RDA under its supervision. Participate in project decision-making that helps prevent or minimize environmental and social impacts and to mitigate them. |
Secure and allocate fund to the project
Support the implementation and monitoring processes at the Regional levels, where the project is located |
All phases of the Project |
National Land Planning Committee |
Responsible for the evaluation of the costs and payment of the compensation, can assist also establishment of committee at district/project area level. |
Support and ensure the consideration of gender, vulnerable groups and disabled households and provision of fair compensation. |
prior to construction/ construction phase |
Ministry of Environment & rural development |
Enforces National Forestry and Wildlife Conservation Low-Act No. 69/2015 and coordinates all multisector environmental issues |
Evaluate the ESIA/ESMP; grant Environmental Approval for the Project; monitor the implementation to ensure compliance with environmental legislation and compliance with the ESMP |
All phases of the Project, from planning and design to the construction and operation and decommissioning; conduct compliance monitoring for the ESMP |
RDA |
Coordinating and organizing the implementation of the project at the national level. Maintain and manage all funds effectively and efficiently for the project |
Involve in the Review and validation of the ESIA report
Monitor the overall physical and financial progress of the project
Involve during handing over before and after construction |
All phases of the Project, from planning and design to the construction operation and decommissioning; conduct compliance monitoring during ESMP |
Awdal Region Administration |
Involved in coordinating the local administration and assist in the overall security of the Region. |
Assign police/ security guards as required & keep the security of the project area/camp |
During study and design including surveying & during construction |
Zeila District |
Involved in the establishment of compensation committee, Grievance Redressing Committee and support the contractor land requests matters for material, workshop and camp site as required. |
Ensure the provision of borrow areas, quarry sites and camp site & their reinstating Ensure also fair compensation to PAPs. |
All phases of the Project |
AfDB |
Overall supervision and provision of technical support and guidance.
Recommend additional measures for strengthening the management framework and implementation performance;
Supervising the application and recommendations of ESMP. |
Review and validation of the ESIA report
Ensure the recommendation and implementation ESIMP as per the AfDB guideline
Provide fund |
During planning, construction and operation |
Contractor |
Compliance to BOQ specification in procurement of material and construction and implementation of CESMP and other required plans and program as stipulated in ESMP |
Implement all contractual requirements as per the guidelines and/or standards |
Construction and operation (defect liability period) |
Supervision Consultant |
Undertake monitoring survey and recommend correction measures at site level |
Ensure the monitoring outputs/recommendations are implemented |
Construction |
- APPROACH AND METHODOLOGY
4.1. Review of Literature, Guidelines, and Previous study
Literatures were reviewed to have some understanding about the ecology and landscape of the road to be upgraded. The literatures include similar ESIA documents and documents which deal about existing policies, environmental guidelines, regulation, environmental proclamations, applicable international conventions and previous studies made on the Country where the project is located.
Key reports, policies and legislations that were reviewed include the Africa Development Bank’s Integrated Safeguards System, particularly the Policy Statement and operational Safeguards, (December 2013), Constitution of the Republic of Somali Land, 31st May, 2001. National Environmental Policy, 2015, Somaliland tenure policy, National Water Policy, National Forestry and Wildlife Conservation Low-Act NO. 69/2015; the Coastal and Marine Resources Policy of Somaliland and National Agricultural Strategic Plan. Please refer chapter 2.0 through 2.10.
The review of relevant documents also informed the development of this ESIA report and assisted the team to have a thorough understanding of the social, economic and environmental situation of the project in relation to the national and regional situation.
4.2. Field Visits
Field visits were made (from March 15 till March 23/2021) to collect and assess primary baseline environmental data and information that would be affected by the very presence of the project. The RDA team led by members from the Project Implementation Unit (PIU) carried additional site visits on 7th April 2025. These include Land use, economic activities, health, education characteristics and the biodiversity (fauna and flora). Topographic maps, digital camera and a hand-held GPS were used to survey the area. Physical observation has been made along the road corridor to acquire primary data of both the physical and biological environment (flora and Fauna).
4.3. Stakeholders Consultation
To acquire social aspects throughout the project corridor, during the field visit consultation were made as annexed. During the consultation, checklists and interviewing methods have been used to gather official information.
The team ensured that all those that have stakes in the project more especially the communities in the project area were consulted to give their views on the project. Specially designed stakeholder consultation data collection tools (checklist) were developed and used during the stakeholder consultation process. Apart from consultations with national level with the Ministry of Transport and Road Development Agency (MoTRA), the consulting team conducted stakeholder meetings and interviews at Zeila and Borama (Region level), and community levels targeting the executive administrators at village and/or town levels, traditional leaders, villagers in the project area, Business owners, transporters, cross border traders, and many other stakeholders. At community level, the consulting team conducted focus group discussions (FGD) and individuals interview with the identified stakeholders. The list of stakeholders consulted during the assignment is summarized in Annex-I.
4.4. Method of Impact Prediction and Evaluation
The purpose of identifying and evaluating the ways in which a proposed project is likely to affect its environment is to predict how those matters can be taken into account during later stages of project preparation, implementation and operation. It is a kind of project appraisal technique aimed at establishing, in broad terms, the nature and likely significance of impacts. Through the identification of key impacts, it is possible to provide guidance to the engineering team concerning the location of areas of high environmental and/or social sensitivity, which should be avoided as far as possible, when identifying potential project concepts or corridors for further recommendations. The objective of prediction is to identify the magnitude and other dimensions of identified change in the environment with a project or action, in comparison with the situation without that project or action.
In the case of the Project under consideration, the primary objective of impact prediction and evaluation is to explicitly identify and (qualitatively or quantitatively) determine the nature and magnitude of the impacts resulting from undertaking the Project.
Once impacts have been predicted, there is a need to assess their relative significance. Criteria for significance include the magnitude of the likelihood of the impact and its spatial and temporal extent, the likely degree of the affected environment’s recovery the value of the affected environment, the level of public concern and the political repercussions.
When choosing prediction methods, one should be concerned about the appropriateness of the methods for the task involved in the context of available resource. Methods or models for prediction could broadly be classified as explorative and normative approaches.
Explorative methods include: approaches like trend analysis, scenarios, analogies and intuitive forecasting. On the other hand, the normative methods work backwards from desired outcomes to assess whether a project, in its environmental context, is adequate to achieve them.
In the context and framework of the road project under consideration, the explorative method is mainly adopted with combination of trend analysis or forecasting, analogies (transferring experience from other similar projects) and experience and professional judgment of the assessor.
The method of evaluation of impacts can be of various types including simple or complex, formal or informal, quantitative or qualitative, aggregated or disaggregated. The most formal evaluation method is the comparison of likely impacts against legal requirements and standards (like air quality standards, water quality standards, noise levels, etc.). The evaluation of the impacts of the project under consideration will depend on the qualitative, and wherever possible quantitative, approaches to evaluate the extent of the impacts in the short- as well as long-term.
4.5. Mitigation Measures
Mitigation measures are measures envisaged in order to avoid, reduce and, if possible remedy significant adverse impacts that have resulted from implementation of undertakings. Implementation of mitigation measures follow the hierarchy given below:
- Avoid impacts at the source;
- Reduce impacts at source;
- Abate impacts at source;
- Abate impacts at receptor;
- Repair impacts;
- Compensate in kind;
- Compensate by other means; and
- Enhance
Figure 2 below shows the generic trend in nature of an environmental impact in time with and without project.
Figure 2: Nature of an Environmental Impact before and After Project Initiation (Glasson, 1999)
As shown in Figure 2, even though mitigation measures are applied or implemented properly, there would still be remaining or residual impacts that cannot be mitigated at all. In other words, environmental resources cannot always be replaced; once destroyed, some would be lost forever. That is why the distinction between reversible and irreversible impacts is a very important one, and the irreversible impacts, not susceptible to mitigation, can constitute particular significant impacts in an ESIA.
5. BASELINE CONDTION OF THE EXISTING ENVIRONMENT
5.1. Physical Environment
5.1.1. Topography
The Zeila-Asha Addo road project is located on the South Eastern part of the Republic of Somaliland. The topography of the surrounding area is generally characterized by flat. The altitude of the project area is in the range from 0 m.a.s.l.(Zeila) to 4 m.a.s.l. (Asha Addo), the average altitude is about 2 m.a.s.l. It is relatively higher near the end area, Asha Addo town, which is about 4 m.a.s.l. The altitude falls to 0 m.a.s.l. on Zeyila town.
Table 10 Pictures showing flat of the project
|
|
Figure 3: Showing Topography (Elevation) along the project area
5.1.2. Geology
Near the coast these terrestrial deposits merge into littoral marine deposits. Stratigraphically the plain is divided into four concentric zones, truncated by the sea coast: (i) the Older Boulder Beds; (ii) the younger gravels; (iii) the Zeila plain "laterite"; and (iv) the Coastal Marine beds.
Project Road
|
Figure 4 Geological map of the project area (Source Geological Map of Somali land)
5.1.3. Soils
The soil Characteristics for the sandy soils, they are with less water holding capacity as they water drains during the rainy season and are with high evaporation capacity during the dry season. The clay soils types are prominent in southern Somalia are low-lying alluvial plains; associated with upstream rivers. Those soils were recognized to leave salts of calcium carbonate on the surface of the ground.
|
Figure 5 Pictures depicting soils in the project area/ On the Coastal low lands |
5.1.4. Climate
The Coastal Plain is a zone with high temperatures and low rainfall. Summer temperatures in the region easily average over 38 °C. However, temperatures come down during the winter as it reaches up to 45 °C during the hottest days. The climatic condition of the project area is arid. The average annual rainfall is 446 millimeters (17.6 in) in most parts of the project area while the coastal zone, which is arid climate and receives less precipitation than the rest of the project area. The coastal range gates rain while the plateau and the mountainous area are in dry condition. This constitutes the period of fresh grazing and abundant surface water.
5.1.5. Water Resources and Drainage
5.1.5.1. Water Resources
The primary source of water is rainfall and the Project Road crosses numerous small drainage which is connected to the Gulf of Aden drainage system. The Project Road drainages drain to red Sea with in the Gulf of Aden river basin. Local enquiries indicate that in most cases these streams are dry outside the wet season except with the back flow accumulations on the coastal land. On the coastal land plain especially to Zeila it is very close to water body and in some cases water transgresses.
The contractors will require considerable volumes of water with various aspects of the works. Water supply for works such as compaction, mortar and concrete works of the road project and these will probably be drawn from water courses adjacent to the road, where flows are limited during the dry season. Wells and springs can be used as an alternative water sources. Maximum care must be taken as those areas are also the main sources of potable water for both human and livestock animals.
|
|
Figure 6 Water Source along the Route on the low coastal plain |
5.1.5.2. Drainage (Watershed)
There are some streams draining across the project site originating from the relatively high altitude areas. The drainage follows from a relatively highlands areas adjacent to the road alignment to the low laying area villages mostly very close to the end portion of the project road and finally drain to the Gulf of Aden Basin System. Dendrite drainage does exist in the coastal land plain transacted by the project area. Furthermore, a number of hydraulic structures are requiring minimizing fluid hazard as the road is to be constructed as a high fill. The numbers of minor drainage crossings traversing the project area are 36 refer Annex 3.
Figure 7 Watershed map of Road Project
5.1.6. Land use and land cover
Assessments done through field observation, and available information from the local administrations transacted by the project road revealed that the major land use/cover of the low land coastal plain which is predominated by arid and semi-arid thorny grass species sparsely existing with some dwindling semi-arid trees in the interface. There exist also in some cases dense bush land forming patches of vegetation inhabiting the wet lands and/or flood plains closest to the red sea. Such vegetation was observed on the section between Zeiela to Asha Addo.
The human settlement in this project area are mainly include per urban towns and villages mixed with cattle camps near the homestead, the houses include grass thatched, wood with Plastic roof houses, concrete structures and Fences, some with corrugated iron and containers which may last for a few years and then renewed. In Asha Addo a number of housing unit which belonging to business (19) and residence (21) are being affected. In total the number of people affected by the project is assumed to be greater 40 (Forty). The villages and towns along the proposed road project are listed in section 1.3, Table 4.
|
|
|
|
Figure 8 Pictures Depicting Land covers of the project area near Zeila, top and loss of structures in Asha Addo (bottom) |
5.2. Biological Environment
5.2.1. Flora
The Zeila-Asha Addo road project is predominantly located in the Awdal Region and has three distinct topographical zones in relation to the vegetation occurrences. The project area belongs to the coastal zone, the description and classification of those zones is indicated below.
Table 11 Vegetation type in the Zeila-Asha Addo Road Project
No |
Name of Zone |
Description |
1. |
Coastal Zone |
This zone is brutally hot, sometimes more than 45-degree Celsius, during the summer, from May to September, and receives lesser rain than other zones in the region. All dry rivers from mountainous zone end up in coastal plains and during the rainy season runs-offs from mountainous zone end up in the low coastal plains and bring alluvial soil. The vegetation in this area occupied by arid climate adapted pants (scattered, dwarf, woody plants less than half a metre high with small hairy leaves and scattered tufted grass and tree species specifically the dry land acacia species include Acacia, Balanites aegyptiaca and Compiphora species. |
|
|
Figure 9 Pictures illustrating the Flora of the project area (Coastal land vegetation) |
|
|
5.2.2. Wildlife
Based on the assessment, the number of wildlife species in the project area is reasonably low as the project area has faced transactions from previously existing vegetation to land degradation mostly occurred on the mountainous topographic zonation. The current relative existence of variety of wildlife species can be correlated to environmental disturbance which had happened in the earliest days. Therefore, more wild life is expected to live in the coastal zone and the mountainous zone than the upland zone.
There is rich vegetation and relatively dense vegetation along the banks of dry rivers in the coastal plains, some of which with running streams. Locals also reported the presence of wild animals such as elephants, Ostrich, Salt’s dick dick and different types of birds. Major wild lives existing in the project area are listed under the Table below. According to locals’ animal movements evident from Zeila partial reserve, this is approximately 20-25 kms long from the project road. The movement is from this reserve to the project area in search food and water.
Table 12 Major wildlife species in the project area (fauna)
No. |
Common Name |
Scientific Name |
Remark |
1 |
Oryx gazella |
High land |
|
2 |
Oryx |
Beisa oryx |
High land |
3 |
Salt’s dick dick |
Madaqua saltina |
High land |
4 |
Mid land and low land |
||
5 |
Loxodonta africana |
Endanger/extinct |
|
6 |
Struthio camelus |
Low land plain |
Source: Zeila District Administration
5.2.3. Environmentally Sensitive Areas
Owing to the extreme variations in climate and terrain, and comprising most ecological systems from altitude 1450 masl to -2masl, the route corridor possesses one of the largest and most diverse plant genetic and wildlife resources in the world. In Somali land, wildlife species live in diverse ecosystems, from the desert lowland coastal plain to the highest elevation of the project end. The Valley and the peripheral lowlands and mid altitudes of the country have also abundant wildlife and plant populations with huge sum of endemism.
Based on the information obtained during first hand interview to dwellers and documents reviewed there are 5 National Parks in the Republic of Somaliland include Daallo Mountain, Hargeisa National Park, however no parks, and priority forest areas along the proposed route corridor. Concerning wildlife sanctuaries (game reserve) there exists Zeila partial reserve, approximately 20-25 kms away from the project road; with a large number of wild lives occupying the harsh climatic condition of the project route areas. Regarding the overall influence area during prioritization has been well screened in all the routes.
Besides to the information gathered regarding fauna and flora verification of the mentioned routes have been done which of the routes are critically in touch with Environmentally Sensitive areas include National Parks and other gazette areas of valuable importance. In this case no National Parks and gazetted areas do exist in the whole influence area.
5.3. Socio economic condition
5.3.1. Administration
The Zeila-Asha Addo road project route is envisaged to link two towns (Zeila and Asha Addo) under the Selal Region (newly established Region); which is not officially/legally approved. Borama & Zeila are serving as Headquarters of Awdal and Selal serve Regions respectively. Following the existing Lowyiaddo-Borama road Lowyiaddo-Garisa belongs to Selal Region and Garisa-Borama belongs to Awdal Region.
Table 13 Settlements along the proposed corridor
Town/village |
Easting |
Northing |
Elevation(m) |
|
1 |
Zeila |
333469 |
1255372 |
2 |
2 |
Asha Addo |
329751 |
1235409 |
4 |
5.3.2. Demography, Ethnicity, Language and Culture
The population of the project road influence area predominantly inhabited by the Somali ethnic groups with Gadabuursi subclan of Dir especially well represented and considered the predominant clan of the Region. There are no major conflicts reported so far between tribes for personal interests. However, there are minor conflicts emanating between tribes for natural resource use.
There are no ethnic minorities or tribal people in and alongside the project counties at area whose traditional lifestyles could become compromised through the development of the proposed Zeila-Asha Addo road project. The Somali group covers 90% of the residents in the project area. It is also noted that the remaining 10% accounts to the non-Somalia groups include Bantus, Bajunis, Ethiopians, Indians, Pakistanis, Persians, Arabs, Italians, Swedes, and Britons, and the Like. The population distribution in the respective as well as religious distributions and languages used are available in the sections following. Somalia has been described as the most ethnically homogenous nation in Sub-Saharan Africa, ahead of Botswana, which is four-fifths Tswana. Somali is the official language Somali, other languages spoken are English, Arabic and Italian.
Somalis constitute the largest ethnic group in Somalia, at approximately 90% of the nation's inhabitants. They are organized into clan groupings, which are important social units; clan membership plays a central part in Somali culture and politics. Clans are patrilineal and are typically divided into sub-clans, sometimes with many sub-divisions. Through the xeer system (customary law), the advanced clan structure has served governmental roles in many rural Somali communities.
Somali society is traditionally ethnically endogamous. So to extend ties of alliance, marriage is often to another ethnic Somali from a different clan. Thus, for example, a recent study observed that in 89 marriages contracted by men of the Dhulbahante clan, 55 (62%) were with women of Dhulbahante sub-clans other than those of their husbands; 30 (33.7%) were with women of surrounding clans of other clan families (Isaaq, 28; Gedabursi, 3); and 3 (4.3%) were with women of other clans of the Darod clan family (Marehan 2, Ogaden 1).
5.3.3. Population in the Project Area
5.3.4. Economic Activity and Livelihood
Livestock rearing is the major source of wealth and prestige and power. Sale of livestock and livestock products provide the main financial capital for agro-pastoralists. This is practiced throughout the year due to the type of livestock reared and fed using crop fodder in paddocks (semi-zero grazing) even during the dry season. Normal rains ensured normal pasture, fodder and crop harvests, which translated to good livestock body conditions, improved livestock production, enhanced marketability of saleable animals and increased incomes and purchasing power of HHs. In spite of this, livestock production is constrained by lack of veterinary services, with agro-pastoralists relying on indigenous knowledge to manage parasites. In some instances, agro-pastoralists purchase drugs from veterinary centers. Women from all wealth groups sell most of livestock products. Those in the middle and better-off wealth groups engage in petty trade and in small business, like selling food, sea cucumber trade, charcoal selling and transportation.
The Coastal Zone dwellers: Livestock rearing in the coastal zone include rearing of camel, sheep and goats. During the summer seasons as the temperature of the coastal zone reaches up to 45oc and the people move in to the mountainous zone. After years of livestock losses from droughts and multiple crises, fish have become a lifeline source of food for nutrition and income for coastal communities. The coasts sandy soils are not suitable for crops, and fishing and livestock are the main livelihoods.
Other Economic Activities: - According to locals, livelihood of citizen at the project areas are also engaged on traditional construction materials mining, catering services and other small scale business which are largely practice by town residents.
5.3.5. Social Services and Infrastructures
It has been observed during discussions in the consultation meeting that access to and utilization of services within the project area and its environs are very limited except telecommunication. In most cases people travel far to access almost any type of service, safe water supply points, health facilities, market centers, grain mill sites, access to credit facilities and the like. Since the Market centres are limited to Zeila and Asha Addo, people use those market centres travelling from the place they live to either Zeila or Asha Addo. However, settlements are very sparse and are available close to those towns, approximately 6 km far from each town. Therefore, settlers travel more than 1 hour to access mills and market centres. All these scenarios negatively impacted the health and wellbeing of family members in general and most importantly women including girls and children.
5.3.5.1. Transportation
All weather roads, mainly of loamy soils, form the main transport systems in project route corridor. These roads run across river beds and are inaccessible during the wet seasons when flash floods render these roads impassable. The situation worsens where rivers/streams intersect. This consequently increases transport costs which indirectly affect the market prices of essential food commodities and a decrease in the general livelihoods of the local communities.
5.3.5.2. Telecommunication
Most of the villages have access to cellular services. About 4 cellular agencies (Telesom, Telecom, Somtel, and Nation link) operate in the Project route corridor. Communication services facilitate remittance flows, trade, information and local money transfers. Agro-pastoralists benefit from the use of telecommunication services by receiving and passing information on rainfall and pasture availability, water tracking and market prices of commodities.
5.3.5.3. Water Infrastructure
The main water sources in the project route corridor are water catchments and shallow wells. Most of the water sources, particularly those bordering Coastal low lands, have at least 1 berkad (water reserviour used in arid area used to collect water during wet season). However, about 20-30% of the berkads were in poor condition (cracked) due to ageing and a small number had been rehabilitated. During most of the year, water is available freely for livestock and for human use, but in the dry (Jilaal) season, water is purchased (at sometimes high costs) for 3-4 months.
Table 14 Water sources along the proposed corridor
No. |
Town/village |
Hand dug well |
Shallow well |
Deep well |
Ponds |
Barked |
1 |
Zeila |
|
- |
1 |
|
|
2 |
Asha Addo |
|
1 |
- |
|
|
Total |
|
1 |
1 |
|
|
5.3.5.4. Health
Health and sanitation condition in an area is an indicator of the living standards of the communities concerned. However, the ratio of health facilities to population in the project is by far below the WHO's standard. The number of health institution in the same are also far below the required size, and accordingly become a major cause for a low health coverage. Locations of health institutions are other problems to improve health coverage. The long distance to the health institution and lack of transport facility seriously limit health coverage. Moreover, rapid population growth could not cop-up with the number of health institutions being constructed. A substantial size of health infrastructures are said to be not operational due to lack of health professional, lack of medical supply and equipment and in some case lack of repair and maintenance of facilities.
The prevalence of HIV/AIDs, which is one of the deadly diseases which have no cure so far, is in the project urban areas. It is believed that communicable diseases will be a major concern during construction since the construction activity attracts an influx of construction work force that will be intermingled with local community. More data and information will be collected to discuss in detail about health and sanitation situations of project affected area and the possible mitigation measures how to mitigate project induced health problems. The health institutions and health professionals along the road towns and/or villages are given in the following Table.
The most commonly reported out-patient diseases are malaria, Helminthiasis, upper Respiratory infections, Gastritis, skin disease, eye disease & diarrhoeal diseases. In general, most of the diseases are related to poor personal hygiene, in adequate & unsafe water supply & lack of basic sanitary facilities. Though it is not included among the top prevailing diseases, HIV/AIDS, CORONA Virus are increasing health and social problems along this road.
Table 15 Health Facilities alongside the road project
No. |
Town/village |
Health Post |
Health Centre |
Clinics |
Hospital |
1 |
Zeila |
0 |
1 |
2 |
0 |
2 |
Asha Addo |
0 |
1 |
0 |
0 |
Total |
0 |
2 |
2 |
0 |
Source: Awdal Region Health Office
Table 16 Health professionals alongside the road project
No. |
Town/village |
Doctors |
Nurses (all type) |
Pharmacist |
Technician (all type) |
1 |
Zeila |
1 |
8 |
3 |
4 |
2 |
Asha Addo |
0 |
3 |
1 |
1 |
Total |
1 |
11 |
4 |
5 |
Source: Awdal Region Health office
5.3.5.5. Education
The distribution of schools and school facilities is therefore an indicator for the level of fulfilment of these basic rights of the communities concerned. The quality of education such as qualification of teachers, student-to-teachers ratio, student-to-classroom ratio, student-to-book ratio, commitment of teachers for their profession, etc. is also important parameters. According to previous studies, student-to-classroom ratios, qualification teachers and their commitment, school facilities, etc. are said to be not good. Data on this issue is not currently available and attempts will be made to collect those data and subsequent analysis will be made during detailed study phase of the project.
It may be good to reach the substantial number of pastoralist community through developing an alternative basic education centres in their areas. This strategy may help achieve a higher impact on the remote and marginalize communities.
Table 17 Number of Schools alongside the road project
No. |
Town/village |
Elementary |
Secondary |
Higher Education |
1 |
Zeila |
1 |
1 |
0 |
2 |
Ashado |
1 |
0 |
0 |
Total |
2 |
1 |
0 |
Source: Awdal Region Education office
5.3.5.6. Historical, Cultural, Religious and Archaeological Resources
New road construction should avoid destroying or downgrading sites of importance be it aesthetic, historical, religious, mineral, archaeological or recreational. Currently there are no historical or cultural sites reported and/or observed; which could be affected by the road project. No Burial places were also observed along the proposed alignment.
6. PUBLIC CONSULTATION AND PARTICIPATION
6.1. Identification of Stakeholders
For the assessed Project, the other categories of primary stakeholders were identified as neighbors such as the community. Secondary Stakeholders were identified as government and Regional and respective town administrations in charge of diverse sectors, and people who will be impacted by the project. This category was also consulted as key informants on sectorial policy, sectorial baseline information development and to advise this ESIA study on mitigation measures to be put in place so as to minimize future impacts in respective sectors. In this category also included local policy makers and Regional officials. Major stakeholders identified with whom consultation was made include:
- Ministry of Transport and Road development in Hargessa City and at Lowyiado
- Road and Transport Agency (RDA) in Hargessa
- Borama Region and major institutions (health, education, water) in Borama City
- Selel Regional Administration
- Village Administration Represented by the Village Heads
- Members from the Project Affected Persons (PAPs)
- Traditional Leaders and other Members from the Larger Community
- NGO’s (International Refuge Council (IRC), World Food Program (WFP)in Zeila
6.2. Consultation Processes and Outputs
Two sets of consultation process was done as part of this ESIA: phase 1 from March 17/20121 till March 19/2021. Additional consultations (phase 2) were done by project team on 7th April 2025.
6.2.1 Phase 1 consultations – March, 2021
The main reasons, for carrying the consultation were:
- To gather the opinions and attitudes of the community towards the project.
- To ensure community participation in such development projects.
- To identify anticipated project impact on the socio-cultural life of the community.
- To obtain commitment of the respective offices/authorities in providing support and cooperation during project planning and through project implementation.
- To ensure that their voices are heard and their views integrated with regard to the project
Discussions and/or meetings have been taken place in Borama (Awdal Region capital), Ziela (Selel Region Capital). Moreover, the benefit of the proposed project had been described to the local communities and administrators adequately and the issues and interest of the communities have been heard and incorporated. The discussions were facilitated by the team of consultants and the discussion points include:
- Briefing about the development plan to implement the road project.
- Propose possible routes and select the pest route
- Discuss about the effect of road development on properties and compensation issues for the PAPs
- Determination of town section width and length
- Getting the opinions and attitudes of the local community towards the proposed project.
- Anticipated positive impacts of the project on socio-economic life of the community.
- The need of community participation at different stages of project activities.
- The means to avoid and/or mitigate anticipated adverse impacts of the proposed project.
The outcomes of the meetings include:
- In general, the consulted officials appreciated the planned road project and highlighted its benefits to the local communities. The meeting participant underlined that construction of the proposed road has a paramount importance for their economic and social development. The local officials’ and community representatives believe that construction of the proposed road will bring socio-economic improvement in the Region and in the country as a whole.
- The participants of the community and states also present their interest concerning the route. They all insisted that we follow as much as possible the existing road underlining socioeconomic importance of the route that gives access to a larger settlement around the project route.
Although the discussions were held at different levels, very similar opinions were expressed with regard to most the points of discussion mentioned above. The discussions were also concerned on the negative and the positive impacts of the project. The following points reflect the general opinion of the consulted community on various positive and negative aspects of the project.
The envisaged Zeila-Asha Addo road project will solve the problem as it introduces asphalt road, which is safer and good riding quality road. People are looking for better access to get better health facilities, market and enhance their economy in general. The present road is impacting their desire because it was taking long time to get their neighbouring towns and State and County administration divisions. Hence they expressed that they are glad to see this development project becoming operational in the near future. Apart from employment opportunity, some of the expectation by the people from the project is that it would help in giving training on best income generating practices such as on diversification of smallholders’ business. Furthermore, the following positive and negative impacts were speculated by the local people /administrators and consultants’ elaborations.
6.2.2 Summery Consultation Outputs
The summery of consultation conducted in Ziela, the district centre of the project area is summarized as below
Zeila
- The Zeila attendants underlined the route should go via Zeyila town as it is the historical port and Regional capital of Selal.
- We understand the benefits of the road; therefore, they will work together to support this development in terms of security, society and environmental aspects
- The centreline of the road should be designed so as to keep trees and houses; otherwise Project Affected Peoples (PAPs) need to get compensation.
- The width and length of town sections shall be determined by the design consultant based on the RDA design manual.
- The “cut of date” shall be decided after the alignment centreline is known.
- PAPs need to be compensated by identifying, registering and implementing compensation process based on the Republic of Somaliland rules and regulations.
Borama
The ideas are almost similar to the outputs of Zeila in all the above aspects except their attitudes given on the alignment of the route.
Figure 10 Pictures illustrating consultation
|
|
||
Consultaion with Zeyila; Selal Region adminstraion |
|||
|
|
||
Consultation in Borama, Awdal Region Capital (Regional Governor) |
|||
|
|
||
Consultation at Zeila district (local residents) |
|||
6.2.3 Phase 2 consultation – May 2025
On 7th April 2025, a team from the Somaliland Roads Development Agency (RDA) met with members from the community of Asha Addo and its surrounding villages to discuss the multinational Nagad/Lowyaddo – Borama road project funded by the African Development Bank. The discussion focused on the following points:
The progress on the implementation of the road project; the construction timelines; the impact on the community and the environment; preparedness of the community as well as resettlement and compensation.
The RDA team led by members from the Project Implementation Unit (PIU) met with the Selel regional administration, village administration represented by the Village Head Mr. Mohamed Said Abdillahi, members from the Project Affected Persons (PAPs), traditional leaders and other members from the larger community. The participants and the community were briefed on the status of the road construction (Lowyacaddo – Zeila Phase I) which is now in the bidding stage while the commencement of the actual works is envisaged in August 2025. The team informed the community that they should expect potential contractors and consultants coming to the area to study and familiarize the terrain and topography of the area before the commencement of the works.
The authority and the community of Asho Addo was updated on the additional funding of the 22km (Zeila to Asha Addo) which will be financed by ADB pending on the appraisal and approval of the Bank’s board. Like the first phase of the road (Lowyaccado – Zeila) there will be PAPs whom their houses, business and properties will be affected by the road alignment. These PAPs were identified during the project feasibility stage and are eligible and entitled to resettlement and/or compensation, therefore each PAP is required to sign a consent form to enable RDA to resettle or compensate the affected persons in line with the Bank’s resettlement guidelines and policies. All PAPs consented and signed the papers.
The Selel regional authority which Asha Addo falls under seemed to be well informed about the status of the road construction thanks to the frequent visits by RDA teams to their region. However, the additional funding of the 22km, environmental and social impact and RDA’s mitigation measures were discussed with them and were all agreed upon. The regional authority represented by the Deputy Governor mentioned that there has been no significant change since the completion of the Feasibility Study, Preliminary and Detailed Engineering Design, Environmental and Social Impact Assessment (ESIA) which was completed in 2022.
However, minor changes have since happened including some environmental degradation caused by flooding on the coastal areas of the region, some of the registered PAPs for Asha Addo have passed away, while some new families have moved into the town and might have erected properties there but according to the agreement between RDA and the regional administration, anyone or any structure that has been constructed around the road alignment after the agreed cut-off date will not be considered for resettlement hence the community were all sensitised on this. Finally, the Governor noted some administrative changes in Asha Addo and Zeila necessitated by the recent presidential elections (November 2024) but, he concluded that these changes have no impact on the road construction and the resettlement works.
Finally, the representatives from the authorities, Asha Addo community in general and the PAPs in particular were all informed about the progress of the Lowyacaddo – Zeila Road construction, the proposed additional funding from Lot II (Zeila – Asha Addo) and the resettlement plans in place. The communities seemed to have appreciative the consultation meetings and vowed to contribute and work closely with the regional authority, RDA, contractor and consultants who will be involved in the project.
Table 17: List of People Met During the Consultation Meetings:
No |
Name |
Designation |
Phone number |
1 |
Abdirahman Yousuf |
Deputy Governor |
+252634534761 |
2 |
Mohamed Said Abdillahi |
Village Head |
+252634659488 |
3 |
Mahdi Haji Hussain |
Chief |
+252634144093 |
4 |
Aidarus Hassan Egeh |
Chief |
+252634588664 |
5 |
Ali Abokor Yonis |
Community Member |
+252634590845 |
7. GRIEVANCES REDRESS MECHANISM
7.1. Need for Grievance Redress
It is human nature people find it hard to lose property and livelihood, even if it is for the good of the public. This feeling of discontent would be further aggravated if their expectations are not met as anticipated or promised in the loss or delay in compensation. Implementation of involuntary resettlement is a complex process, which can involve conflicts, disagreements, and grievances on the part of PAPs and other stakeholders, mainly because it involves the expropriation and compensation of land and other assets. To deal with such emerging issues, a Grievance Redress Committee will be constituted with a membership inclusive of representatives of the PAPs and those of local administrative units.
Both the Government of Somaliland laws as well as the AfDB OS2 include procedures for dealing with concerns or complaints rose by individuals or groups about the project land acquisition and associated mitigations, such as payment of compensation and livelihood restoration measures.
Therefore, to ensure that the basic rights and interests of PAPs are protected, that concerns are adequately addressed and that entitlements are delivered, a Grievance Redress Mechanism has been designed for the Asha Addo road project presented in the following sections.
The most important step in conflict resolution is conflict avoidance. Therefore, the consultative and participatory nature of decision-making under the implementation of this RAP is aimed at reducing the occurrence of disagreements and conflicting positions. For instance, where disagreements do occur, it is important that they are resolved quickly before positions harden and the conflict escalates.
Different approaches may be required according to the level that any conflict has reached. Recognizing that the earlier a potential conflict is recognized and dealt with, the higher the chance of a successful outcome. These phases of conflict development and appropriate interventions can be summarized as follows:
Conflict avoidance |
Consultation & participation in planning, decision making |
Simple disagreements |
Informal negotiation, discussion, and mediation |
Conflict development |
Consult Regional, Towns/District Resettlement Committee Representative |
Conflicting positions taken |
Reference to Grievance Redress Committee |
Intractable conflict: |
Refer conflict to regular court |
The best means of addressing any complaints or claims is through dialogue. Thus, when a PAP has a grievance, she/he will first discuss the issue with the Resettlement Committee (RC). If the RC is not able to address the grievance, the complaints should be passed on to the Grievance Redress Committee. The grievance redress system for the implementation of the RAP is outlined below.
7.2. Types of Grievances
It is recognized that, complaints are likely to arise which if not dealt with in a timely and fair manner, could lead to conflict between the community and other stakeholders, notably RAD, but also other Federal and Regional government entities.
Potentially, several types of grievances or disputes could arise that present a risk to a successful implementation of the Project. The following are some of the potential sources of project related grievances:
7.3. Sources of Grievances
In most road projects, the most common issues that can cause delays and calls for dispute resolution mechanism include:
- Technical errors during data entry that leads to delays in processing of compensation for the PAP
- Misidentification of assets or land owners due to registration errors or inaccurate or misleading information during assets surveys;
- Disputes among PAPs over ownership of an affected asset.
- Rejection of a compensation award by PAPs as inadequate or not representative of market value
- disagreement over the valuation or quality of an asset where compensation is payable;
- Emerging unprecedented cultural issues (e.g. relocation of graves, payment for compensation in a polygamous marriage etc)
- rates applied for monetary compensation for affected property;
- ownership disputes of the land and the assets affected;
- Implementation of the livelihoods restoration program (e.g. eligibility and entitlements to restoration measures etc.);
- disagreement over the type, quality and quantity of measures applied to achieve livelihoods restoration;
- impacts of the construction and operation of Road Project; and
- Disagreement over the cut-off date applied.
The grievance redressing procedure is developed to meet the Government of Somaliland legal requirements relating to grievance resolution and international requirements for grievance management and is in line with AfDB’s Operational Safeguards. The following section sets out the procedures to be followed to manage grievances caused as a result of Asha Addo road project implementation.
7.4. Grievance Management Approach
Although it remains largely informal and traditional, communities in the Project area have effective community-based conflict resolution processes. For some of the potential conflicts that may arise in relation to the Project’s land acquisition, it is both less expensive and more appropriate to consider the use of a traditional conflict resolution mechanism. For example, issues such as PAPs’ land ownership (title deed) and boundaries between plots owned by different PAPs can best be resolved through traditional conflict resolution processes within the community. To enhance the effectiveness of the community-based conflict resolution processes, RAD will work with Local administration and community elders and develop a detailed protocol for their use.
RAD shall also maintain a transparent process that is gender and special needs-responsive, culturally appropriate, and easily accessible. This system shall be available to all project-affected people at no cost and without retribution. The proposed approach for grievance resolution provides multiple entry points to the system. For minor grievances between PAPs, or between PAPs on the one hand and other community members on the other, RAD will refer the matter to relevant community elders for resolution. If the grievances are deemed major, then RAD will facilitate mediation or negotiation between the parties.
Where a grievance relates to RAD’s management of the RAP process, the community-based resolution is not appropriate. Grievances relating to compensation will be dealt with in accordance with the grievance mechanism set out in this RAP. Project construction and operation impacts shall be managed in accordance with the grievance redress mechanisms prepared and presented below. Any grievances rose to RAD staff relating to construction or operational grievances will be referred to the appropriate entity in accordance with the grievance mechanism.
Based on consensus, the procedures will seek to resolve issues quickly in order to expedite the receipt of entitlements, without resorting to expensive and time-consuming legal actions. If the grievance procedure fails to provide a result, complainants can still seek legal redress procedures.
7.5. Grievance Redress Mechanism
Grievances relating to land acquisition, livelihood restoration, compensation, and related matters will need to be separated from grievances relating to the impacts of the project construction and operation on local communities. The former concerns the Project Office, the local government, and PAPs and/or their representatives. However, the latter mainly concerns the Contractor and subsequently, the developer (RAD), although the Project Office will continue to play a role in the resolution of such concerns.
Grievance Redress Committee (GRC) will be established with a membership consisting of representatives from PAPs, local administration units, RAD, etc. Grievances should be settled amicably whenever possible. The main function of the Grievance Redress Committee is to provide a forum for the PAPs to air their dissatisfaction arising from the compensation or implementation process of the project. This is an informal forum within the Resettlement Committee to fast-track addressing of emerging issues in a project that can derail a smooth implementation of a project. The Committee is to receive complaints from the PAPs through the project office either verbally or in writing and they endeavors to address the issue to the satisfaction of the complainant.
The redress committee will compile registers of all complaints received from the PAPs at the project office, the actions taken and the decisions arrived at. Initially, the Resident Engineer and his staff with secretariat of the GRC will handle the complaint. The GRC will examine the case (by hearing the testimonies of both parties) and pass its decisions and inform the PAP. If required, the GRC would undertake a site visit and ask for relevant information from the project Authorities, etc. Failure to arrive at a satisfactory answer, then the RE will refer the matter to the GRC that meets periodically. Whereas the GRC is constituted of people outside the Project Office of the Resident Engineer, the latter will be a coopted member together with the Contractors representative for expeditious resolution of the complaints regarding the project.
The GRC plays a critical role of providing PAPs with a fair playground to present their complaint over the compensation or its implementation process. Initially, the Resident Engineer and his staff with secretariat of the GRC will handle the complaint. If the matter is not resolved to the satisfaction of the complainant, then the RE will refer the matter to the GRC that meets periodically. This is an informal forum to fast-track addressing of emerging issues in a project that can derail a smooth implementation of a project. The Committee may receive complaints from the PAPs through office of the Resident Engineer verbally or in writing and it tries to address the issue to the delight of the complainant. If the issue could not be resolved amicably on time, the complainant then may have recourse to the Resettlement Committee. And if not yet satisfied by the decision of the RC, the complainant reserves the right to seek redress from the Court of law, but this option is lengthy and costly in most cases.
The findings of the GRC are binding on the RC. All complaints received by GRC will be recorded and logged into the complaints register. Under the proposed project, a set of forms are developed to be used for recording grievances, and the actions taken are prepared, as listed below (if required shall be translated into the local language).
- Grievance Statement Form
- Grievance Receipt Acknowledgement Form
- Grievance Investigation Form
- Grievance Investigation Outcome Form
The grievance mechanism applies to all complaints related to Asha Addo road project activities; and is comprised of the following steps:
Outline of the Grievance Redress Mechanism Steps
- Step 1 – Receive and Record Compliant (using the Grievance Receipt Standard Form). The grievance shall be registered in a ledger/ log book at the project site.
- Step 2 – Review Complaint and Allocate Actions (Complaints are screened, and actions then are allocated to investigate and resolve the grievance or refer the matter to the next level)
- Step 3 – Notify Complainant of Proposed Resolution (notify the complainant that the complaint has been received, how it is being dealt with, by whom and an approximate estimate of how long the process might take (this must happen within 5 days).
- Step 4 – Take Action and Update Complainant (undertake the proposed actions for resolution and update complainant when it is complete).
- Step 5 – Closeout & Lessons Learnt (occurs when both parties are happy with the proposed solution).
- Step 6 – Update Project Grievance Records (ongoing) (using standard forms, grievances will be maintained and stored including information for any outstanding actions)
- Step 7 – Reporting (to concerned/ defined parties).
Detailed feedback and Grievance Redress Mechanism (GRM) will be prepared by RAD. It will ensure that the grievance mechanism will include the necessary procedures for disclosure and resolution of environmental and social-related grievances of the project. Based on the AfDB’s Grievance Redress Service (GRS), project-affected communities and individuals may submit complaints regarding a Bank-financed project to the project grievance redress mechanism, appropriate local grievance mechanism, or the Bank’s corporate GRS. The broad procedures for dealing with grievances and complaints are illustrated schematically in Figure 9.
7.6. Dispute procedure
The filing of grievances has to be carefully recorded and properly kept. Complainants should be assisted by GRC members so that they can be able to address their issues in a satisfactory manner. Once a complaint is received at the complaints desk in the project office, it is registered and given a reference number for ease of following up. The Office will evaluate the application and determine whether the issue can be handled administratively or the Committee has to meet over the matter.
Where the Committee has to be convened, all its proceedings are recorded and minutes prepared of the deliberations. The minutes have to be confirmed at the next meetings and authenticated by the full sitting. All the resolutions agreed upon by the GRC have to be given prompt action so that the delay will not cause negative impact on the activities of the road project. Some issues that arise in-course of the project implementation are dealt with as they arise.
During the first months of the project, it is advised that the committee meet regularly every week since it will be common to receive many complaints from PAPs, which require the frequent presence of members for immediate actions and decisions. The frequency of the meetings can be reduced as the issues to be addressed decrease and the meetings may now be scheduled on periodic basis over months, until the completion of the project. The guiding principle in addressing the complaints is that the matters must be addressed as expeditiously as possible and within the dispute resolution mechanism, not more than a week should be taken before a decision is communicated to the complainant.
7.7. Role of PAP’s Representatives in Grievance Redress Committee
The involvement of PAPs in Grievance redress committees is very important in resolving disputes and complaints locally through engaging with their fellow affected community members. Among the many, they play the following key roles.
-
- Accept the grievances of the PAPs and provide an early solution to those they are able to;
- Bring in serious matters to the attention of the RC; and
- Inform the complainants about the progress of their grievances and the decisions made by the RC.
8. IMPACT IDENTIFICATION AND EVALUATION
8.1. Identification of Impacts
According to the visual assessment of pavement condition on all existing roads, visual structural condition survey of drainage structures and an inventory of road furniture carried out. The existing pavement condition of the existing gravel road project road alignment can be divided in to two sections. The road along the flat and coastal plain i.e. from the start of the project Zeila-Asha Addo is an earth trail or earth track with no defined alignment that stretches on alluvial sand deposit with poorly ride able section. This section of the alignment has been interrupted by several small span seasonal streams emanating from the mid land highlands, where at some locations the road is going in the stream course. The Soil on low lying coastal Palin; which is close to the sea looks whitish due to salt deposited after the recession wetness evaporates.
The consultant believes the condition survey record will indicate the relative performance required during construction and stress sustainability of the road bed soils under the existing traffic.
Currently the road is rendering traffic movement mainly big trucks coming from Djibouti and medium vehicles coming from within the Somaliland towns and villages; which can cover the product transport of import and export goods although it is deteriorated. The road is therefore under the status of losing the required quality and causing traffic damages, generally under very poor condition. It is envisaged to improve the standard and the quality of the existing poor condition gravel road to bitumen standard (DC5).
The construction and operation of this road will result in a variety of environmental and social impacts. Many of the changes will be beneficial, particularly in terms of increasing the reliability of road transport and the potential to develop the local economy. There will nevertheless be some adverse impacts on the physical, biological and socio-economic environment. Major potential adverse impacts include:
Construction Phase
- Loss/clearing of vegetation due to land acquisition for camp establishment, material site development and widening of the main road in narrow areas (It is estimated about 220m2 areas is needed to construct 22km road.
- Impacts on flora and fauna for development of sites indicated under number 1
- Loss of land under various uses due to land acquisition for the right of way, realignments, culverts, detours, quarries and borrows pits, and for construction works. Which is expected to be more than 220 km2
- Increased soil erosion and sedimentation due to ground disturbance and alteration of drainage systems.
- Impacts of flooding due to ground disturbance and waterlogging effects
- Alteration to the drainage regime and water pollution due to redirecting of watercourses at culverts operation of quarries and borrow pits, disposal of wastes, etc. The road is located in flat land (coastal land plain) where dendrite drainage crosses the alignment. It is proposed to be constructed in a high fill road which also requires provision of hydraulic crossings to equalize water flow from both sides
- Air and noise pollution due to construction activities and operation of construction machinery. This is more pronounced in Asha Addo and Zeila towns, those towns are very small and all social services including religious places are very close.
- Increased risks of communicable diseases due to influx of people to the project area; water stagnation due to ground disturbance and disposal of material waste as the project site is totally malaria prone area.
Operation Phase
During operation many of the impacts are beneficial include travel time reduction, improvement in riding quality, reduction of dust and mud and improvement in drainage. The major negative impact expected is traffic accident.
8.2. Evaluation of Impacts
A checklist method is proposed for evaluation of environmental impacts of the project road. A comprehensive checklist covering the range of impacts that may be associated with the road projects was developed (see Table 8.1.). The checklist is designed to suit as much as possible the particular environmental condition in the project areas and the nature and scope of the proposed project works. For each potential impact, the checklist provides (subdivided into groups according to the phase (pre-construction, construction, post-construction) in which they may occur): The character of the impact in terms of 6 key parameters (impacts type, effect, duration, change, periodicity and areal extents), and The evaluation of potential impact significance level based on 4 common characterization parameters (not significant, small, moderate or major).
Table 18 Identification and Evaluation of Potential Environmental Impacts: Zeila-Asha Addo Road Project road project
|
|
|
||||||||||||||||||||
Effect |
Duration |
Change |
Areal extent |
Significance level without mitigation |
||||||||||||||||||
|
No change |
Beneficial impact |
Adverse impact |
Unknown |
|
Indirect |
Short |
Medium |
Long |
Reversible |
irreversible |
continuous
|
periodic Adverse impact |
Irregular
|
Localized
|
Widespread |
Extensive |
Non- signif |
Small |
Moderate
|
Major
|
|
CONSTRUCTION PHASE |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Impact on land resources (ROW) |
|
|
X
|
|
X |
|
|
X |
|
|
X |
|
|
|
X |
|
|
|
|
|
X |
|
Impact on vegetation |
|
|
X |
|
X |
|
|
|
X |
X |
|
|
|
|
|
X |
|
|
|
X |
|
|
Wild life impediment |
|
|
X |
|
X |
|
|
|
X |
X |
|
|
|
|
X |
|
|
|
|
X |
|
|
Pollution of water |
|
|
X |
|
X |
|
|
|
X |
|
X |
|
|
|
|
X |
|
|
|
|
X |
|
Water resource conflict |
|
|
X |
|
X |
|
|
X |
|
X |
|
|
|
|
X |
|
|
|
|
X |
|
|
Health and public safety |
|
|
X |
|
X |
|
|
X |
|
X |
|
|
|
|
X |
|
|
|
|
X |
|
|
Solid and liquid waste |
|
|
X |
|
X |
|
|
X |
|
X |
|
|
|
|
|
|
|
|
|
X |
|
|
Occupational health |
|
|
X |
|
X |
|
|
X |
|
X |
|
|
|
|
X |
|
|
|
|
X |
|
|
Construction spoils |
|
|
X |
|
X |
|
|
X |
|
X |
|
|
X |
|
|
X |
|
|
|
X |
|
|
Air pollution |
|
|
X |
|
X |
|
|
X |
|
X |
|
|
|
|
|
X |
X |
|
|
|
X |
|
Noise pollution |
|
|
X |
|
X |
|
|
X |
|
X |
|
|
|
X |
|
X |
|
|
|
|
X |
|
Coastal land plain activities |
|
|
X |
|
X |
|
|
|
|
X |
|
|
|
|
X |
|
X |
|
|
|
X |
|
OPERATION AND MAINTENANCE PHASE |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Noise pollution |
|
|
X |
X x |
|
|
|
X X |
|
X |
|
|
|
|
|
X |
|
|
|
X |
X |
|
|
|
|
|
X |
|
|
|
|
X |
X |
||||||||||||
Traffic safety |
|
|
X |
X |
|
|
|
X |
|
X |
|
|
||||||||||
Spill of hazardous materials (fuel & oil) |
|
|
X |
X |
|
X |
|
X |
|
|
X |
|
|
|
|
X |
|
|
|
|
X |
|
Runoff from drainage structures |
|
|
X |
X |
|
|
|
X |
|
X |
|
|
|
|
X
|
|
|
|
|
X |
|
|
Coastal land activities on Red sea |
|
|
X |
|
|
X |
|
X |
|
X |
X |
|
|
|
|
|
X |
|
|
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
9. IMPACT MITIGATION AND ENHANCEMENT MEASURES
9.1. Positive Impacts of the Project
The proposed project would provide several positive impacts. The major positive impacts are described below:
9.1.1. Local Income-generation During Construction
The creation of temporary jobs can be considered as a positive impact of the road construction to the local people. Some individuals may gain skills that can be applied in other road construction projects too. Further direct opportunities include entrepreneurial development as a result of the increased population and increased infrastructure usage. This includes items such as supplies, accommodations, food outlets, restaurants etc. The general economic growth of the region due to increased access and increased traffic flow on the envisaged road and adjacent roads will create further indirect job opportunities. Markets will be much more accessible, thereby providing people the opportunity to increase production and access to external markets with their products.
The creation of regular wage employment in the rural parts of project area is important, even though it will be on a relatively small scale, at relatively good rates of pay and for a limited period, since there are currently few other opportunities available. The presence of the workforce, who is likely to be relatively cash-rich compared with the majority of the rural population, will undoubtedly encourage individuals to set up stalls to supply food and other consumables at worksites. Businesses in the local towns will also benefit financially through supplying goods and services to the workforce when they are on leave, as well as through the contractors purchasing some of the food requirements of the base camps. It is recognized that for those individuals who are fortunate enough to gain employment and those who provide goods and services, the impact on family incomes will be relatively high.
Although labor recruitment is a matter for the contractor, who has the right to determine whom he shall and shall not employ, he should be formally encouraged to hire locally wherever possible, in so far as this is compatible with his skill requirements, in order to maximize the benefit distribution and social acceptability of the project. He should also be encouraged to procure supplies from local sources to the maximum extent possible in the circumstances.
9.1.2. Gender Impacts
Women in the project area could work as daily labourers and in other similar activities during project implementation and operation. Female-headed households in particular could benefit from the employment opportunities that would be created. They also gain working skills that can be applied in other similar activities. It also helps to develop confidence and self-sufficiency among women who are involved in the road project work. The other benefit of the project for women during construction of campsite and residential units is that it would help to start small businesses such as opening tea houses, meal houses and small shops, etc. Therefore, in order to harness these advantages, the project will encourage use of local manpower giving priority to women.
In general, the project will have socio-economic environment positive impact due to the development of project in the area. The project will create rural employment. In addition, social welfare program shall be enhanced or created. These include provision of medical facilities educational facilities, water supply, recreational amenities for the employees. New villagers will be established and local people will be consulted in all activities and eventually to make them partner in the developmental process.
During employment of workers, in the recruitment process of the organization, local people will be given preference on the basis of their qualification and experience and as per the requirement of project. Gender equity will be ensured as much as possible in the employment process and this will be properly managed.
9.1.3. Economic Growth
With enhanced implementation of the upgrading project not only the economy of the local people would be improved, but also will contribute its share to better facilitate overall economic growth of the country. Since the road will be better condition the project will create favourable environment for drivers to drive safely and timely to deliver exchange of goods.
9.1.4. Traffic Safety
Improvement of road quality will provide better road condition for driving heavy tracks thereby facilitating the overall activity of the area. Besides to this there will be a reduction of travel time, traffic accident and vehicle operation cost. Improved road has a tendency of increasing accidents than before improvement; which shall be considered and minimizing by introducing traffic management plan.
9.1.5. Local Social and Socio-economic Benefits during Operation
With regards to transportation, the villages belonging to Selal Region and the towns are now least developed in terms of connectivity, accessibility and mobility. Most rural people and villages in those Regions are either have connection to motorable transport or use even wheel-based intermediate technology modes. As a result, the large majority of rural population mostly depends on inefficient traditional modes such as walking, human porter age and pack animals along a network of narrow, untended, century’s old local footpaths, trails and tracks. This traditional mode is relatively burdensome, expensive, time consuming and unsuitable for modern development needs. As a result, it is very difficult for these isolated communities and villages to easily obtain their daily domestic needs, profitably market their surplus products, to buy basic needs and inputs at fair prices and to get access to vital socio-economic services.
Therefore, by far the most significant beneficial impact of the project is expected to be a major improvement in social and socio-economic conditions for all who live on or relatively close to the new road. The construction of the new realignment road will have a number of vital contributions to rural development; supports poverty alleviation schemes, improves food security, improves marketing, enhances export earnings, promotes balanced growth, strengths stability and help social development. At present there is little incentive for most smallholder agro-pastoralist to produce anything other than subsistence crops, since access to markets where cash crops can be sold is difficult, particularly for those who live more than a few kilometers from one of the towns.
The new road is likely to lead to the introduction of transport services, which operate between the main centers of population and also from between a town market and villages along the road, as has been the case following construction of other similar roads in the country. This may open up the prospects for crop diversification in the long-term, with short-life, but relatively high value produce such as vegetables becoming a financially viable option. It is also anticipated that younger people would likely enroll in school and go on to higher educational facilities due to better transportation with access to road, services will be improved. Different goods and services will likely be available raising the standard of living and way of living. Electricity and other services often follow the road and will likely change the way of life of people in existing population centers. Benefits will also be realized in terms of improved access to hospital and other medical services.
Continued enjoyment of the benefits of the upgraded road will only be achieved if it is maintained in an improved state. It is therefore recommended that: the Somaliland Roads Development Authority should ensure that adequate budget and resources are allocated to routine and periodic maintenance of the project road, and that an effective maintenance program is initiated and sustained.
9.2. Negative Impacts
9.2.1. Impacts on Water Pollution from Sanitary and other Wastes and Spillages
Groundwater and ponds are used for potable supply purposes throughout the project area for drinking, washing purposes and cattle watering. There are also water supply ponds along the project road as indicated under the baseline information above. Pollution of these resources may arise at or close to the basecamp (to be selected during construction) or work sites as a result of inadequate provision of sanitary and waste facilities, and accidental or deliberate spillage or leakage of polluting materials. Such pollution adversely affects those who depend on local water resources. Inappropriate disposal of refuse and some materials used in construction can also lead to public and animal health hazards.
Surface water and ground water may be contaminated by improper utilization or storage of construction materials which are toxic or hazardous, including chemical or petroleum products such as diesel fuel and lubricants. Contamination could also arise from lack of proper treatment and disposal of sewage from construction work camps. Sand and gravel removal from river beds is not expected to have any adverse impacts. River beds are traditional sources for sand and gravel and long have been in use.
With regard to hygiene and environmental health, normal sanitary and cleaning facilities will be provided within the premises. The management will carry out periodic health checkup of workers of all sections.
Mitigation measures
Water source pollution is of potentially high significance along the project road. Therefore, the contractor should take all appropriate mitigation measures to minimize pollution risk.
- Require the contractor to make specific and adequate provision for the disposal of sanitary (septic tanks) and other wastes (waste disposal pits) in such a way as will not result in any form of pollution or hazard to human or animal health.
- The contractor to take all reasonable precautions to prevent spillages and leakage of materials of fuel and oil with the potential to pollute water resources. The measures should be maintained in an effective condition throughout the life of the base camp.
- Specifically prohibit washing of vehicles and plant (crusher/asphalt), campsite or adjacent to any water sources. All washing to be carried out at camp areas away from water sources.
- The contractor is responsible for cleaning up any pollution caused by his activities and the payment of full compensation to those affected.
9.2.2. Impacts of Competition for Water Resources
During construction there will be minor effects on surface water hydrology due to the creation of new cuts, drains, and culverts. However, the majority of this work will be carried out during dry periods when there is no or little surface flow. The contractor will require substantial volumes of water for various construction purposes such as adjustment of moisture content of fill, road sub-base and base courses, and watering of haul routes to suppress dust. In addition, the water requirements at the basecamps will be relatively high, although these will be much lower than those needed in connection with construction. It is probable that some of the contractors' water requirements will be met by abstraction from watercourses. During the dry season, most watercourses which the road crosses have no flow and where there is, it will be very low and any scale withdrawals by contractor could reduce water availability to existing users. Construction works might increase sediment loading temporarily on nearby rivers and streams. However, sediment concentrations and loads naturally vary over a wide range during the year, and as a result, aquatic communities will be able to adapt to temporary high sediment loading conditions very easily.
Mitigation measures
- Impact can be minimized satisfactorily by requiring the contractor to make his own arrangements for water supply which will not affect the rights of others, and to provide an alternative supply if interference does occur. Most of these impacts can be controlled by good house-keeping, appropriate response to emergencies, and effective clean-up of accidents and spills. It is therefore, recommended that the following measure should be adopted:
- The contractor is responsible for making his own arrangements for water supply for construction and other purposes without affecting the quality or availability of groundwater or surface water resources to existing users. In the event of there being any valid dispute regarding the effect the contractor's arrangement has had on the water supply of others, the contractor shall be responsible, at his own expense, for providing an alternative supply to those affected, which is not inferior in quantity or quality to that previously enjoyed.
- Such impacts could be alleviated by prohibiting from using water points and water sources that are used by the public and allowing the contractor to use his own sources by tapping ground water (boreholes) or by creating storage during the rainy seasons.
9.2.3. Impacts on Natural Vegetation
Construction
Otherwise, there are no sensitive area such as National parks and priority forest areas transacted by the proposed project road. The primary concern is actually vegetation clearing to create space for (1) road works at RoW, (2) Campsites, (3) material sites – quarry / borrow pit, (4) access roads to the camp or material sites, (5) temporary diversions along the road. The second concern would be demand for wood and poles for structures being constructed and increased demand for fuel wood by project workers. There is also a real possibility of the workforce engaging in illegal timber extraction to the determent of the environment if adequate controls are not applied. Policing of the existing vegetation from a conservation viewpoint is probably ineffective as a result of manpower and other constraints.
- Maintaining of solitary trees on the road sides.
- Planting new trees as a compensation for the lost plantation, but leaving enough space for the future road widening and maintenance purposes.
- Constructing road sections, which pass through cropped areas after the harvest
- Relocating roadside infrastructure such as power lines, telephone wires, water points etc. before construction of the road commences if any.
Operation
The impact of deforestation shall be exacerbated after construction (operation stage) as many people start to live alongside the relatively vegetated areas due to better access and / or access facilities. After construction people will be migrating to this area and there will be big demands for charcoal and house building. This will increase deforestation and will destroy the natural habitat.
Mitigation Measures
It is recommended to adhere to principles of environmental conservation during the construction period in order to avoid excessive destruction of vegetation and disturbance of trees. Therefore, to minimize the destruction of trees and natural vegetation, it is recommended to:
Construction
- Avoid excessive destruction of trees and other vegetation;
- Consider the location of mature trees during route selection for the access road construction and land clearing for quarry and borrow sites; and compensate the lost natural vegetation as appropriate.
- Prepare a plan to remove mature trees in borrow and quarry sites so as to obtain optimal benefits from harvested timber;
- Compensate in cash for the loss of privately-owned mature trees and by replanting
- Specifically prohibit quarrying, borrowing, spoil disposal and camping within the boundaries where trees are available.
- The contractor will be responsible for any fire accident caused by his activities within the woodland and riparian trees;
- The contractor is responsible for the conduct of his workforce in relation to environmental protection matters and to specifically prohibit unnecessary felling of trees.
Operation
During operation stage; the RDA should design awareness program against any charcoal selling especially in high land vegetation and other forest areas along the corridor.
9.2.4. Impact on Land Resources
The road construction project basically follows the existing alignment; however additional land acquisition will be required for widening the existing variable width of the road to a standard width as the existing width varies. The existing alignment in most cases 4-6m. It requires about 4-6 additional width assuming the design to be 10 metres. Land acquisition will also be required for material access roads and for the stretches taken up for construction in order to allow easy flow of traffic. For these uses, land under housing units and utilities in town sections, and natural vegetation will be mostly affected. In addition, land loss will be related to extraction of construction materials. Several sites in communal land have been proposed as sources of materials for construction of the road.
In Asha Addo a number of housing unit which belonging to business (19) and residence (21) are being affected. In total the number of people affected by the project is assumed to be greater 40 (Fourty), which need to be contested. This necessitates the requirement of Resettlement Action Plan (RAP) as mitigation measure for loss of land, crops and assets.
Mitigation Measures
- Provide adequate and timely compensation for the land to be acquired for housing units and utilities in town sections and quarries and borrow sites if land belongs to individual local dwellers.
- In case there is natural vegetation, implement also the mitigation measures indicated on section 8.3.3.
- Put structures at the outlet of drainage ditches to dissipate runoff energy.
- Re grass and replant road side cuts on mountainous areas.
- Rehabilitate already established gullies on the road sides.
- Informing owners beforehand that their agricultural produce are at risk.
9.2.5. Air Pollution
The major effects on air quality during construction would be an increase in suspended particles (fugitive dust) from quarry activities, crushing and concrete batching plants, and construction works (blasting, excavation as well as movement of heavy machinery, trucks and trailers) construction equipment and emissions from vehicles have the potential to negatively affect air quality in the vicinity of the construction sites and access roads. The burning of wastes also has the potential to affect air quality. However, impacts from these activities will likely be confined to areas within 200-300 meters downwind from construction sites and these operations take place in most cases locations away from major settlement areas. However, the construction workers will be susceptible for dust pollution.
Mitigation Measures
The potential risk to air pollution will be mitigated or minimized by implementing the following measures:
- Water access road section and construction sites to reduce fugitive dust generation to prevent damage to dwellings and avoid nuisance to persons. Construction roads should be watered near settlement/towns of Asha Addo and Zeila on a set schedule depending upon weather conditions;
- Construction machinery should be well maintained to minimize excessive gaseous emissions. The engines of construction machinery and vehicles will be inspected and adjusted as required to minimize pollution levels;
- Avoid disposing of any volatile chemical to the air such as bitumen;
- Burn waste and/or garbage in designated areas and away from nearby villages and in accordance with Applicable Law; and
- Avoid the burning of materials such as tires, plastic, rubber products or other materials that create heavy smoke or nuisance odour. Do not burn material which produces toxic gases.
- Discarding construction wastes at a waste disposal sites.
- Preventing the generation of air pollutants during the construction period by watering during crushing and screening of aggregates.
- Watering of the detour roads.
- Avoiding the burning of materials such as tiers, plastic, rubber products or other materials that create heavy smock or nuisance odour.
- Avoiding disposing of any volatile chemicals to the air.
- Minimizing smoke emanating from vehicle’s exhausts by keeping them in good condition
9.2.6. Noise Pollution
Sustained noise levels during construction are expected to be much higher than the ambient noise levels in the project area. Noise and vibration result from construction activities in general but particularly from operation of heavy machinery including vehicles, excavation equipment, concrete batching plants and crusher plant sites. Other sources of noise will be explosives used to prepare the foundations for construction of the road and access road. Noise intensities from blasting at quarry sites, or in areas of rock excavation range from 80 to 100dBA at source. Sustained noise levels during construction are expected to exceed 70dBA at a distance of 200 meters from source.
There are sensitive noise receptors like schools, health instructions and worship places in Asha Addo, Zeila and the construction areas and consequently, noise generated from the construction sites will be a major annoyance to a large number of people in major settlement areas. Although noise impacts on communities are unlikely, excessive noise is likely to impact the construction workers in and around the construction areas. The construction area harbors only limited number of wildlife. However, wildlife that inhabit the project area are not familiar with the noise level related to the traffic and construction activities and some may move away from the noise and eventually return to the area when construction is complete.
Mitigation Measures
The potential noise impacts will be mitigated or minimized by adopting the following measures:
- Equipment normally producing high levels of noise should be suppressed and screened when working within a distance of 200 meters from any settlement, clinic, religious places or other sensitive noise receptors;
- Repair or replace if mufflers and other noise control devices of construction equipment and vehicles are defective; and
- Provide adequate hearing protection to construction workers exposed to noise
9.2.7. Impacts of Public Health and Safety
As part of the project areas are lowland, streams and ponds of various sizes. This kind of topographical has created varying grounds for different kinds of diseases, particularly water born & water related ones. Major health problems of the project area are reported to be different types of infectious diseases & water related disease. According to the information obtained from respective administration health offices along the project road, the public health status is not improving over time as the health service did not reach the grass root communities on the project area. For this reason Common public safety issues are causes of problems related to public health safety include:
- Spread of communicable disease – HIV, COVID etc, water born and water based diseases will be aggravated during construction
- Massive pollution of water sources could also cause water borne diseases such as Amoebiasis, Typhoid
- Traffic related accidents moving vehicles and lack of facility and training for workers engaged in heavy machineries and areas (quarry and borrow).
- Construction worker’s safety issues since as they involve the use of sharp objects, noisy machineries and dusty environment
- Shortage of facilities like toilets and catering facilities for construction workers.
Health and risk management should be done to avoid unnecessary impact on human health. Elements of health and risk management include the following:
- Provide clean water for drinking and domestic use and avoid use of contaminated water.
- Among the above vector born diseases such as malaria and sexually transmitted diseases(STDs) including HIV are expected to increase as a result of road construction processes due to influx of work force in to the reception area/community. There are non-Muslim dwellers and construction work forces in the project area towns.
On the centre of villages, there may be a problem of crossings for both human and livestock during construction and operation phases; since the people residing on those areas are not aware of traffic accidents unless mitigated.
Mitigation Measures
Health and risk management should be done to avoid unnecessary impact on human health. Elements of health and risk management include the following:
- Providing health facilities (mobile clinic or first aid service depending on the size of workforce).
- Provision of adequate speed breakers on the major village sections (the entrance of Zeila and Asha Addo)
- Providing health education on how to arrest HIV and other sexually transmitted diseases.
- Implementation Country code of CORONA virus alleviation measures
- Providing health facilities (mobile clinic or first aid service depending on the size of workforce).
- Providing health education on how to arrest HIV and other sexually transmitted diseases.
- In cases of Malaria outbreak:
- Provide mosquito nets and insect repellents.
- Drain out any water holding areas around the camp and settlement areas.
- Avoid pond formation that creates conducive environment for mosquito breeding.
- Using appropriate and clear signs on the road.
- Limiting the speed.
- Creating traffic awareness to the people, particularly at schools and churches.
- Allocating temporary traffic police/flagman.
- Providing detour roads wherever possible.
- Informing parents to keep children from exposure to the construction area.
In terms of public health services, the project will have a great benefit mainly by improving access to health facilities. The negative impact due to increases in STDs, especially HIV/AIDS will be mitigated by education and sensitising the local population. The following are additional measures that will be taken to minimize the public health and safety impacts:
- Awareness creation program for workers to protect them against these diseases.
- Provisions of protective means such as condoms
- Provide clinical services
- Medical Check ups
- Instructions and enforce safety procedures of the plantation to avoid accidents and injuries.
- Use personal protective equipment to safeguard the safety of the workers.
- The work place and premises should be kept clean and safe.
- Good hygiene and sanitation of the working area.
- Training personnel involved in the different stages of the project activities about safety procedures and emergency response plans associated with their task.
9.2.8. Impacts of occupational Health and Safety
Road construction is a high-risk occupation due to the intensity and volume of works that involve heavy machinery, quite a large number of vehicular traffic, hazardous substances and chemicals etc. Accidental spillage of inflammable or toxic chemicals, hazardous substances like fuel & oils could create safety and health risks to project workers as well as local people. Injuries may also arise from road traffic accidents, which have the potential of harming construction workers. Other sources of injuries are noise, vibration and heat, and also lubricants some of which contain solvents with potential to cause skin irritation and allergies, respiratory disorders and acute poisoning. These impacts would be mitigated by adopting the proposed mitigation measures listed below.
Mitigation Measures
- Provide first aid materials, suitable for dealing with minor injuries at all work sites
- Make a deal with local health facilities to handle any emergency cases of the workforce.
- Provide all the required protective clothing and safety equipment. This clothing and equipment should be specified in the contract document and shall include as a minimum: High visibility vests for workers directing traffic; protective boots and gloves for the workforce undertaking concrete mixing work; protective boots, gloves and masks for the workforce
- Create awareness and continuously remind labour force about safety, signage and maintenance of diversions,
- Occupational hazards involved in project related to dust pollution, noise pollution, and injuries from field activities, will be avoided or highly minimized. The management of the project will give the necessary guidelines for safety against these occupational hazards as per the national guidelines.
9.2.9. Impacts on Wildlife Corridor
Destruction of valuable wildlife and impediments to wildlife movements is also expected during construction and/or operation of the Project Road. The project road construction will be a temporary impediment to existing wildlife movements. It will be more sever during operation as the quality of the road will be improved which enables moving traffic to rush at high speed.
Mitigation Measures
- Totally avoid locating quarry and/or borrow pits, camp sites and other workforce stations, development of water points within the bush land habitats, especially in the upland plain.
- Avoid Horn and noise on wildlife
- Use controlled blasting using chemicals, if badly required
- Educate/orient construction workforce that hunting is completely forbidden and illegal
- Equipment normally producing high levels of noise should be suppressed and screened when working within a distance of 200 meters from sensitive noise receptors/wild life habitats;
9.2.10. Impacts of Coastal land plain Activities on Red Sea
Construction
This impact will occur during both construction and operation. Activities such as earth work and other ground disturbance as a result of machinery ground interactions will exacerbate erosion and sedimentation. Grease and oils during maintenance and servicing of vehicles and /or machineries will also induce impacts of pollution on the water bodies which ultimately affects the phytoplankton and zooplankton life inside the same.
Operation
During operation passengers traveling from Zeyila to Asha Addo and visa vise may rest for limited time and require resting rooms or may pollute the coastal land/coastal land marginal land with solid and liquid waste which pose pollution.
Mitigation Measures
- Install mobile toilets and solid waste disposal barrels in areas where bus stop bay areas
- Implement all the mitigation measures related to erosion and sedimentation impacts to minimize sediment load especially arising from the upland plain.
- Implement grassing alongside the road as sediment trap
- Avoid car washing and change of used oil in the marginal land of the sea
9.2.11. Impacts of Construction Spoils
It is expected that the project works will generate large quantities of spoil material especially due to widening of the carriage width and some minor geometric design adjustments. It is likely that there will be occasions when unsuitable existing road material will need to be removed and disposed of.
Material eroded from the spoil itself can be deposited in water courses, with adverse effects on channel morphology and capacity to convey flood flows, deteriorates the water quality of receiving streams.
Mitigation Measures
- Contractor should dispose spoils on designated spoil disposal areas by the Engineer
- Avoid side tipping of material spoils on to adjacent farmlands, grazing lands, homestead plantation.
- Avoid spoil disposal in wetlands and drainages (rivers, streams and other water bodies)
- Avoid spoil disposal in vegetated areas
- All solid and liquid wastes generated from the road construction activities should be managed properly.
- Solid wastes must be collected and burnt in a burn pit specially created for this purpose. These burning pits must be placed away from the populated areas and covered up after completion of the construction work.
- Mobile toilets and waste barrels for non-biodegradable wastes such as plastic bottles and other solid wastes alongside the road in the coastal land zone.
- All the used oil from the plant and equipment must be collected and burned or sent for reprocessing by the contractor after collecting in barrels. The environmental inspector has to ensure the proper implementation of these activities and submit a report on the status of environmental management to the client.
Major impacts, their mitigation during planning/design stage, construction, operation and decommissioning phases including the responsible body for implementing, monitoring indicators and evaluation and their corresponding cost is depicted under the Tables below
Table 19 Environmental and Social Management Plan
CONSTRUCTION |
|||||
Predicted Impacts |
Proposed Measure |
Responsible body |
Estimated Cost, USD |
M& E Indicators |
Time line |
Negative Impacts |
|||||
Properties of 40 project affected people-PAPs could be expropriated. This impact high in towns |
|
Designer, RDA, Contractor, Supervisor |
Included in Design and RAP costs;
|
Complaints from PAPs |
Construction |
Vegetation removal along the Road (within right-of-way), access roads, quarries, borrow areas, etc. |
|
RDA, Contractor, Supervisor |
51000 |
Number of trees planted/ removed |
Construction |
Impediment to movement of wildlife and accidents involving wildlife moving Ostrich, Salt’s dick dick in the project road corridor. |
|
Designer, RDA, Contractor, Supervisor |
18,000 |
Number of accidents |
Construction |
Pollution of surface and ground water as a result of earthwork operations and improper handling of hazardous materials |
|
Designer, RDA, Contractor, Supervisor |
Inincluded in Design and construction cost |
Occurrence of fuel and lubricants contamination |
Construction |
Conflict on water source computation with locals |
|
Contractor |
included in construction cost |
Construction water availability and local people complaints |
Construction
|
Impact on public health safety |
|
Designer, RDA, Contractor, Supervisor |
22,000 |
Cleanliness of Camps and workplaces
Management of Waste disposal
KAP survey and awareness status |
Ditto |
Improper waste (solid as well as liquid) management will cause health problems |
|
RDA, Contractor, Supervisor |
15,000 |
Periodic inspection of solid and liquid disposal in camp site |
|
Impact on occupational health and safety |
|
RDA, Contractor, Supervisor |
Included in construction cost |